Red Hook WatchIndependent Community Resource

Sewer Operations Report — Late January/February 2026

2 versions2026-03-09attached document

Latest version

Village of Red Hook SEWER OPERATONS REPORT

Late January/February 2026

We had operational meetings on Jan. 22, Feb. 5, Feb. 19 where we reviewed sewer operations. Present were Village Engineer Robert Flores, Sewer Operator Les Coon, DPW Foreman Jake Smith, Sewer Clerk Jen Cavanaugh, and Mayor Karen Smythe

SEWER OPERATIONS:

ODORS – Throughout February we had a series of odor complaints Feb. 5, 13 & 20 from Red Hook Estates, Feb. 15, 27 (2) from Smith Street. One from Kent Rd. appears to have been a private septic system issue; all the others appear to have come from our EQ tank. Last March 2025, a system to pull the air from the EQ tank into the odor control system was installed. On Monday, March 2, it was discovered that the blower fan that operated this system had failed. The operator thought they had confirmed it was working but it turns out it was not. A replacement fan was installed Monday (3/2/26) afternoon.

NY ALERT NOTIFICATIONS/NOTICE OF VIOLATIONS

On Feb. 20 & 24 there were NY Alerts and Notice of Violations submitted to DEC regarding partially treated discharge. 2/20 was both Plant 1A & 1B. 2/24 was Plant 1B. In both cases solids were lost through the clarifier causing the sand filter to clog and overflow into the clearwell – meaning that the full treatment didn’t happen prior to discharge. DEC issued a letter, attached. To simplify, the flow into the WWTPs was too much for the plants to handle. The design of the plant called for an EQ tank that is too small for proper operations. When the influent comes in all at once, without the extra EQ tank capacity, there is nowhere else for the influent wastewater to go. It is impossible to predict when these extra flows are going to occur. The interim solution prior to the expansion of our EQ tank capacity, is to set up a remote high-level event alarm system so the operator is alerted immediately to a high-level situation. A modem with cell service that will allow for internet access has been purchased and programmed. The full system with floats and sensors is scheduled to be installed and operational by 3/5&6. Once the ground thaws, Archtop will install underground fiber to supply the internet for the future. There is also a second temporary, above ground EQ tank waiting for back-ordered parts. Once these parts arrive, there will be additional temporary EQ capacity to help mitigate the extra flows.

Until we are able to permanently add additional EQ tank capacity, we are operating with several temporary solutions. The alarm system should help to catch these overflow events faster, thus preventing partially treated discharges to occur. This plant design has little if any margin for error.

In late February, we discovered that NYS’s NY Alert system was not distributing all our submitted alerts. We reached out to NY Alert and they did discover that DEC had made an error. From NY Alert:

  • After a lot of digging, we have determined DEC made an error when creating the security role that had an incorrect setting preventing you from issuing alerts to the required group despite the template being set up properly. The setting has been corrected, and it should work properly going forward. NY Alert Support

COLLECTION SYSTEM – FROZEN PIPES

With the unusually extended period of temperatures below freezing this winter, we found that some of the pipes from the septic tanks connecting to the forcemains have frozen – the majority of these are tanks in parking lots leaving less insulation from the ground to protect the pipes from freezing. Unfortunately, the design did not call for adequate insulation or depth to ensure these pipes wouldn’t freeze. When the system

called for the pump to come on, the wastewater was not able to go through the pipe, causing the alarm to go off. These tanks must be pumped out by the Village waste hauler until the thaw. We are looking forward to the warmer weather and will be considering options for solutions for next winter.

REMAINING REPAIRS NEEDED

There are some repairs that still need to be made including replacing the return activated sludge valve in plant 1B (old plant) on the West side. When an attempt was made to replace the valve, the surrounding pipe broke. So further work needs to be done to replace the pipe as well as the valve. The UVs have been repaired. There is one sensor that is not reading correctly that needs to be fixed. One of the generators needs a new switch.

ENGINEERING AUDIT

Delaware Engineering has conducted an audit of sewer operations. We are waiting for the report.

WEBSITE UPDATE

The WWTP page under the Sewer Department on the Village’s website is updated regularly. There is a lot of information and documents on this page. Deputy Mayor Kjarval has completed a refresh of the page, reorganizing the data, making it easier to navigate and find information.

Changes between versions

2026-03-092026-03-09
minor edit+33

Minor wording changes were made to the NY Alert Notifications section.

  • Changed 'Noncompliance Reports' to 'Notice of Violations' in the NY Alert Notifications header
  • Changed 'Notice of Violation, attached' to 'letter, attached' in the NY Alert Notifications section
Show red-line diff
## Village of Red Hook SEWER OPERATONS REPORT ## Late January/February 2026 We had operational meetings on Jan. 22, Feb. 5, Feb. 19 where we reviewed sewer operations. Present were Village Engineer Robert Flores, Sewer Operator Les Coon, DPW Foreman Jake Smith, Sewer Clerk Jen Cavanaugh, and Mayor Karen Smythe ## SEWER OPERATIONS: ODORS – Throughout February we had a series of odor complaints Feb. 5, 13 & 20 from Red Hook Estates, Feb. 15, 27 (2) from Smith Street. One from Kent Rd. appears to have been a private septic system issue; all the others appear to have come from our EQ tank. Last March 2025, a system to pull the air from the EQ tank into the odor control system was installed. On Monday, March 2, it was discovered that the blower fan that operated this system had failed. The operator thought they had confirmed it was working but it turns out it was not. A replacement fan was installed Monday (3/2/26) afternoon. ## NY ALERT NOTIFICATIONS/NOTICE OF VIOLATIONS On Feb. 20 & 24 there were NY Alerts and NoncomplianceNotice Reportsof Violations submitted to DEC regarding partially treated discharge. 2/20 was both Plant 1A & 1B. 2/24 was Plant 1B. In both cases solids were lost through the clarifier causing the sand filter to clog and overflow into the clearwell – meaning that the full treatment didn’t happen prior to discharge. DEC issued a Notice of Violationletter, attached. To simplify, the flow into the WWTPs was too much for the plants to handle. The design of the plant called for an EQ tank that is too small for proper operations. When the influent comes in all at once, without the extra EQ tank capacity, there is nowhere else for the influent wastewater to go. It is impossible to predict when these extra flows are going to occur. The interim solution prior to the expansion of our EQ tank capacity, is to set up a remote high-level event alarm system so the operator is alerted immediately to a high-level situation. A modem with cell service that will allow for internet access has been purchased and programmed. The full system with floats and sensors is scheduled to be installed and operational by 3/5&6. Once the ground thaws, Archtop will install underground fiber to supply the internet for the future. There is also a second temporary, above ground EQ tank waiting for back-ordered parts. Once these parts arrive, there will be additional temporary EQ capacity to help mitigate the extra flows. Until we are able to permanently add additional EQ tank capacity, we are operating with several temporary solutions. The alarm system should help to catch these overflow events faster, thus preventing partially treated discharges to occur. This plant design has little if any margin for error. In late February, we discovered that NYS’s NY Alert system was not distributing all our submitted alerts. We reached out to NY Alert and they did discover that DEC had made an error. From NY Alert: - _After a lot of digging, we have determined DEC made an error when creating the security role that had an incorrect setting preventing you from issuing alerts to the required group despite the template being set up properly. The setting has been corrected, and it should work properly going forward._ **NY Alert Support** ## COLLECTION SYSTEM – FROZEN PIPES With the unusually extended period of temperatures below freezing this winter, we found that some of the pipes from the septic tanks connecting to the forcemains have frozen – the majority of these are tanks in parking lots leaving less insulation from the ground to protect the pipes from freezing. Unfortunately, the design did not call for adequate insulation or depth to ensure these pipes wouldn’t freeze. When the system called for the pump to come on, the wastewater was not able to go through the pipe, causing the alarm to go off. These tanks must be pumped out by the Village waste hauler until the thaw. We are looking forward to the warmer weather and will be considering options for solutions for next winter. ## REMAINING REPAIRS NEEDED There are some repairs that still need to be made including replacing the return activated sludge valve in plant 1B (old plant) on the West side. When an attempt was made to replace the valve, the surrounding pipe broke. So further work needs to be done to replace the pipe as well as the valve. The UVs have been repaired. There is one sensor that is not reading correctly that needs to be fixed. One of the generators needs a new switch. ## ENGINEERING AUDIT Delaware Engineering has conducted an audit of sewer operations. We are waiting for the report. ## WEBSITE UPDATE The WWTP page under the Sewer Department on the Village’s website is updated regularly. There is a lot of information and documents on this page. Deputy Mayor Kjarval has completed a refresh of the page, reorganizing the data, making it easier to navigate and find information.

References

This document cites or incorporates the following separate documents:

  • 2026-04-13DEC Noncompliance Report Forms
    — pinned to version dated 2026-04-13
    Document B is the formal DEC noncompliance report form filed in response to the violation events described in Document A; they are separate artifacts in different slots (operational report vs. regulatory filing).
  • 2026-04-09Report Noncompliance Event – WWTP Plants 1A & 1B Solids Loss
    — pinned to version dated 2026-04-09
    Document B is a formal DEC noncompliance report filed in response to the violation events described in Document A; they are separate artifacts serving different slots (operational report vs. regulatory filing).
  • 2026-04-09Report Noncompliance Event — SPDES Permit Violation
    — pinned to version dated 2026-04-09
    Document A is an operational report describing sewer system issues including the Feb 20/24 violations; Document B is the formal DEC noncompliance report filed in response to those same violations—they are separate artifacts serving different slots (internal reporting vs. regulatory filing).
  • 2026-04-09Report Noncompliance Event — Village of Red Hook SPDES Permit Violation
    — pinned to version dated 2026-04-09
    Document B is a formal DEC noncompliance report filed in response to the violation event described in Document A; they are separate artifacts serving different slots (operational report vs. regulatory filing).
  • 2026-02-01DEC Violation Report Forms
    — pinned to version dated 2026-02-01
    Document B is a DEC violation report form that Document A references and attaches as supporting evidence of a separate regulatory action, not a revision of the same document.
  • 2026-02-202026 02 20
    — pinned to version dated 2026-02-20
    Document B (dated 2026-02-20) is a separate operational notice/alert that Document A (dated 2026-03-09) later references and reports on as a past event; they are distinct artifacts in different slots (immediate alert vs. retrospective operations summary).
  • 2026-03-09Mayor's Report — February 2026
    Both are independent status reports covering different operational areas (sewer operations vs. mayor's general report) issued on the same date; they share a topic area (village operations) but are distinct board documents with different purposes and scopes.
  • 2026-04-13NYS DEC SPDES Wastewater Facility Report — Plant 1 (March 2026)
    Document B is a separate regulatory filing (SPDES monthly report) that documents the same facility operations as Document A, but they are distinct artifacts serving different purposes—one is an internal operations summary, the other is a mandated state compliance report.
  • 2026-04-13EPA Discharge Monitoring Report (DMR) — February 2026
    Document A is an operational narrative report covering sewer system issues in late January/February 2026; Document B is the EPA Discharge Monitoring Report (DMR) form for February 2026—two separate regulatory documents that both address the same time period and facility but serve different slots (operational narrative vs. mandatory EPA compliance reporting).
  • 2026-02-262026 02 26
    Document B appears to be a working/draft version of operational notes, while Document A is the finalized Sewer Operations Report presented to the board; they document the same operational period but occupy different slots (working notes vs. board report).
  • 2026-02-01NetDMR Submittal Confirmation Email — March 29, 2026
    Document B is a separate administrative confirmation of a regulatory filing, while Document A is an operational report; they share a topic (sewer compliance) but are distinct documents serving different purposes.
  • 2026-02-01EPA DMR — February 2026
    Document A is an internal operational report on sewer system issues; Document B is a separate EPA Discharge Monitoring Report (DMR) that the sewer operations would reference/comply with, but they are distinct regulatory documents serving different purposes.
  • 2026-03-09March 9 2026 SEWER OPERATIONS REPORT
    Both documents are sewer operations reports dated 2026-03-09 covering the same period (late January/February 2026) with identical subject matter and structure; Document B appears to be a revised/finalized version of Document A.

Referenced by

These other documents cite or incorporate this one:

Recurring pattern

These other chains use the same template but are separate decisions: