Town of Red Hook Greenway and Trails Committee Monthly Report — March 2024

1 versions2024-04-08attached document

Document

Village of Red Hook Wastewater System
Red Hook Commons
Average Daily Flow :
0.015 MGD (Million Gallons per DayVillage of Red Hook
0.039 MGD (Million Gallons per Day)
February 2024Required SamplesResult-Compliance
-BOD (June 1 - Oct 31)1.3 mg/L-5 mg/L
-TSS<2.50mg/L-10 mg/L
-NH3<0.50-Oct 31) 1.81 mg/L (Nov 1 - May 31)
-Fecal Coliform0.98 mg/L (June 1 --200/100 mL
-Dissolved Oxygen<1.00/100 mL-0 mg/L Minimum
--8.0 mg/L--
--7.--
Deficiencies
Anoxic Mixers
Placed Aeration tank back in service, system is working properly
Sand Filter Rebuild
Sand Filters have never been rebuilt or media replaced. Should price and schedule for the near future.
Train Down for Review
Reviewed Train and found air getting into the aeration tank. Currently working on pricing for replacement parts. Train scheduled to go back online on 1/8/2024
Pump Station
Pump Station pumps clogging issues have been an issue for some time. Pump Station mixing should be implemented to help with pump failure and pump station pump outs.
Backflow Prev.
R
l
Facilities backflow Preventor in need of replacement.

|Additional Notes:|||||

References

This document cites or incorporates the following separate documents:

  • 2024-04-08NYS DEC Wastewater Facility Operation Report — February 2024
    Document A is a committee monthly report summarizing facility operations and deficiencies; Document B is the official NYS DEC regulatory compliance report for the same facility and month—two separate documents serving different purposes (internal committee review vs. state regulatory filing).

Referenced by

These other documents cite or incorporate this one:

Recurring pattern

These other chains use the same template but are separate decisions: