Red Hook WatchIndependent Community Resource

Life Insurance Plan for Full-time Employees

1 versions2024-04-25#op-_04252024-445-05inline resolution

Document

Life Insurance Plan for Full-time Employees

RESOLVED

  • the existing life insurance plan is offered to fulltime employees at the employees cost as a payroll deduction

Changes between versions

2024-10-172024-10-17
substantive change+3236

The document has transitioned from Work Change Directive No. 1 to No. 2, representing a new scope of electrical work and a different allowance allocation.

  • Title changed from 'Work Change Directive No. 1' to 'Work Change Directive No. 2'
  • Description changed from 'Remove the existing well control panel enclosure and clean up abandoned wiring' to 'Furnish and install the conduit and wiring for the chem feed. Chlorine analyzer, and chart recorder.'
  • Allowance number changed from 'ALLOWANCE # 1' to 'ALLOWANCE # 2'
  • Not-to-exceed cost changed from '$4,750.00' to '$4,462.50'
  • Remaining Allowance Balance changed from '$20,250.00' to '$15,787.50'
  • Date of Issuance changed from '10/4/24' to '10/11/24'
  • Scope of work expanded from enclosure removal to installation of conduit and wiring for specific components (Chlorine analyzer, chart recorder, etc.)
Show red-line diff
**WORK CHANGE DIRECTIVE NO. 21** PROJECT: Village of Red Hook Water System SCADA Upgrades Project DATE OF ISSUANCE: 10/114/24 EFFECTIVE DATE: 10/114/24 OWNER: Village of Red Hook OWNER’s Contract No.: Contract #1E ENGINEER: Delaware Engineering ENG Project No.: 21-2337 CONTRACTOR: Avanti Control Systems, Inc. Contract Date: 10/17/23 You are hereby directed to proceed promptly with the following change(s): ## Description(s): Item #1: FurnishRemove the existing well control panel enclosure and installclean theup conduit andabandoned wiring for the chem feed. Chlorine analyzer, and chart recorder. ## Attachement(s): Item #1: Avanti Proposal Allowance Proposal #21 – dated 10/4/24. ## Payment(s): These items will be paid out of the Contract #1E Allowance: Item #1: A not to exceed cost of **$ 4,462750.5000** as provided in Avanti Control Systems proposal dated 10/4/24. ## Contract Time: Item #1: Estimated increase (decrease) in Contract Time: Substantial Completion 0 days Final Completion 0 days Changes in work requests and associated costs shall comply with Articles 11 and 13 of the General Conditions. If a claim is made that the above change(s) have affected Contract Price or Contract Times any such claims shall be processed in accordance with Article 13 of the General Conditions. When signed by the Owner, Engineer/Architect and received by the Contractor, this document becomes effective IMMEDIATELY as a Work Change Directive (WCD), and the Contractor shall proceed with the change(s) described above. |When signed by the Owner, Engineer/Architect and received by the Contractor, this document becomes effective<br>IMMEDIATELY as a Work Change Directive (WCD), and the Contractor shall proceed with the change(s) described<br>above.|When signed by the Owner, Engineer/Architect and received by the Contractor, this document becomes effective<br>IMMEDIATELY as a Work Change Directive (WCD), and the Contractor shall proceed with the change(s) described<br>above.| |---|---| |Recommended for Approval by ENGINEER:<br>Date:<br>10/11/24<br>—™<br>).<br>p<br>~~—~~<br>~~Qian,~~|| |Authorized for OWNER by:<br>Date:<br>~~—~~<br>~~Qian,~~|| |Accepted for CONTRACTOR by:|Date:| **WORK CHANGE DIRECTIVE** **PAGE 1 OF 1** Mayfield Commerce Park 204 Co. Hwy 157 Gloversville, NY 12078 Ph: (518) 921 4368 ## **PROJECT ALLOWANCE** ## **CONTRACTOR:** Avanti Control Systems, Inc. 204 Co. Hwy. 154 Gloversville, NY 12078 > **ALLOWNCE #** 21 > **DATE** 10/4/2024 ## **PROJECT:** The material and labor listed below have been added to the project under contract allowance monies. Village of Red Hook Contract 1E Water Systems SCADA Upgrades SRF Number 18-787 (Engineer Pin 21-2337) **==> picture [481 x 352386] intentionally omitted <==** **----- Start of picture text -----**<br> ||||||||| |---|---|---|---|---|---|---|---| |QTY|UNIT|DESCRIPTION|PRICE|AMOUNT| |a|1|Lot|a|Stilsing Electric Proposal No.42|$| 4,250500.00 $| 4,250500.00| |PO|1|Each|Avanti Control Systems 5% Markup|$212250.5000 $|212 250.5000| |OO| |PO| |OO| |PO| |OO| |PO| |OO| |PO| |OO| |a|OG| |A|OO| |PL| |A|Oa|OC| |PL| |OO| |a|A|OO| |a|OO| |OO| |A|OC| |PO|Note|: Stilsing Electric - Removal of exisitng electrical enclosure.| |WE AGREE hereby to make the change(s) specified above at this price|$|4,462750.5000| |Contract Allowance Amount|$|25,000.00| |Previous Allowance Balance|$ 20,250.00| |Remaining Allowance Balance|$ 15|20,787250.50| **----- End of picture text -----**<br> **==> picture [188 x 21] intentionally omitted <==** **----- Start of picture text -----**<br> ||| |---|---00| |Timothy Tesiero VP|10/4/2024| |Your Name, Title|Date| **----- End of picture text -----**<br> Signature Date of Acceptance **Accepted** - The above prices and specifications of this change are satisfactory and are hereby accepted. All work to be performed under same terms and conditions as specified in original contract unless otherwise stipulated. Signature Date of Acceptance **==> picture [214 x 74] intentionally omitted <==** **----- Start of picture text -----**<br> ¢ TALI INC.<br>CERTIFIED N.Y.S. WBE<br>**----- End of picture text -----**<br> ## **CHANGE ORDER PROPOSAL___4_____PROPOSAL____2____** Date:July 8/27/16, 2024 **Attn:** Tim Tesiero Avanti Control Systems Re: Red Hook WaterSCADA SCADAupgrades project. **Stilsing Electric Inc.** is pleased to provide you with the following change proposal for additional electrical work on the above referenced project for the lump sum price of **$4,250500.00** . The scope of work for this change proposal is detailed below. ## SCOPE OF WORK: - InstallRemove conduitexisting original well control panel enclosure & clean up all abandoned wiring in the control building for Chlorine Analyzerwithin. - Install conduit12” &x wiring12” inwireway to reconnect all existing conduits that go out to the controlwell building for Chart Recorderheads. - Install conduitnew &conduits wiringas inrequired theto controlconnect buildingcircuits forpassing Flowthrough Meterold cabinet. - InstallDispose conduitof &existing wiring in the control building for Chemical Pump. - All conduits to be PVCcabinet. - All work will be done during the normal working hours of 7AM to 3:30 PM Monday thru Friday unless otherwise noted. No additional work will be performed without formal approval. Upon approval, please sign & return:________________________________ date___________ Thanks, ## George Gipp Project Manager / Estimator Cell 518-491-9273 **5 0 0 S O U T H S T , R E N S S E L A E R , N Y 1 2 1 4 4 5 1 8 - 4 6 3 - 4 4 5 1** Page 1 ~~ee~~