Building / Planning & Zoning Department Fees
| Type | Prior Fee | Proposed Fee | Notes |
|---|---|---|---|
| Administration | Nonelisted | Residential - $50.00 | |
| Commercial - $100.00 | Fee applies toallbuilding | ||
| permits. | |||
| Bounced/Returned Check | None listed | $25.00 | |
| Construction- Residential | $0.35 / sf; $100.00 minimum | $0.75/ sf; $200.00 minimum | Certificate of Occupancyor |
| Compliancefeeswill be | |||
| collected with Building Permit | |||
| Application | |||
| Construction - | |||
| Commercial | $0.50 / sf; $200.00 minimum | $0.95/ sf; $300.00 minimum | Certificate of Occupancyor |
| Compliancefeeswill be | |||
| collected with Building Permit | |||
| Application | |||
| Decks / Porches Open | $0.35 / sf; $100.00 minimum | $0.75/ sf; $150.00 minimum | |
| Demolition Permit | |||
| (when not associated with | |||
| construction) | Residential - $100.00 | ||
| Garages/Barns - $150.00 | |||
| Commercial - $200.00 | Residential(minor)(<500 sf | ||
| excluding dwelling)- $100.00 | |||
| Residential(major)(>500 sf | |||
| excluding dwelling) - $200.00 | |||
| Garages/Barns - $150.00 | |||
| Commercial -$200.00 | Valid for 6 months | ||
| Barns/Pole | |||
| Barn/Shed/Detached | |||
| Garage | $0.35 / sf; $100.00 minimum | Residential - $0.75/ sf; | |
| $200.00 minimum | |||
| Commercial -$0.95/ sf; | |||
| $300.00 minimum |
Page 1 of 12
Date Adopted: XX, YY 2026
| Type | Prior Fee | Proposed Fee | Notes |
|---|---|---|---|
| Solar Energy Collection | |||
| Systems (Photovoltaic | |||
| Panels), Roof or Ground | |||
| Mounted | $0.35 / sf; $100.00 minimum | $0.75/ sf; $150.00 minimum | Roof Mounted, building |
| permit only. | |||
| Ground Mounted by Planning | |||
| Board Approval | |||
| Fence Permits | $100.00 / 1st100 linear feet | ||
| $0.35/ linear footthereafter | No change | Sketch, specifications, & proof | |
| ofDigSafeNYrequired. | |||
| Agricultural Structures | N/A | No change | Proof of Ag Exemption/Status |
| Required at time of | |||
| submission. | |||
| Building without a Building | |||
| Permit | |||
| (Post Built Permit) | Double the Calculated Fee | No change | |
| Stop Work Order Violation | $500.00 per day | $500.00 | |
| Stop Work Order Lift | $250.00 | No change | |
| Certificate of Occupancy | $50.00 Residential | ||
| $100.00 Commercial | $100.00 Residential | ||
| $200.00 Commercial | Collected with Building Permit | ||
| Application | |||
| Temporary Certificate of | |||
| Occupancy | $250.00 Residential | ||
| $300.00 Commercial | No change | Valid for 3 months | |
| Abstract C/O / | |||
| Municipal Search | $100.00 | Residential -$150.00 | |
| Commercial - $200.00 |
Page 2 of 12
Date Adopted: XX, YY 2026
| Type | Prior Fee | Proposed Fee | Notes |
|---|---|---|---|
| Driveway Permit | |||
| (Village Roads) | $100.00 | No change | |
| Generator | $75.00 | $100.00 | |
| Electrical Work / Upgrade | $100.00 | No change | |
| Solid Fuel Permit: | |||
| Wood, Coal, Pellet | $100.00 | No change | |
| Operating Permits | $100.00 | No change | |
| Swimming Pools: In- | |||
| ground, Above Ground | In Ground =$200.00 | ||
| Above Ground =$150.00 | |||
| Spa/Hot Tubs =$100.00 | In-Ground =$250.00 | ||
| Above Ground =$150.00 | |||
| Spa/Hot Tubs =$100.00 | Backflowpreventerdevice | ||
| required.Reduced Pressure | |||
| Zone (RPZ) backflow | |||
| preventers requires annual | |||
| inspection. Certification sent | |||
| to BuildingDepartment. | |||
| Hens/Honeybee Permit | |||
| (Zoning§200.18.1) | $25.00 | No change | |
| Sign Permit | $100.00 flat | $125.00 | |
| Site Inspection | None listed | Residential - $100.00 | |
| Commercial - $150.00 |
Page 3 of 12
Date Adopted: XX, YY 2026
| Type | Prior Fee |
|---|---|
| Fire Inspections | $150.00 up to 2,500 sf; |
| 2,501—5,000 sf = $200.00 | |
| 5,001–10,000 sf = $250.00 | |
| Additional FireInspections |
-
If the Fire Inspector must inspect premises a third time to ensure compliance with the Code an additional fee of $100.00.
-
If the Fire Inspector must inspect premises a fourth time to ensure compliance with the Code an additional fee of $125.00.
-
In the event of non-compliance with the Fire Inspector's recommendations after a fourth visit the property owner is subject to fines and expenses imposed by the Village Justice Court as per Village Code § 95.
| Proposed Fee | Notes | |
|---|---|---|
| $150.00per Unitup to 2,500 | ||
| sf; | **See note below regarding | |
| 2,501 | 2,501—5,000 sf = $200.00 | additional inspections |
| 5,001 | 5,001–10,000 sf = $250.00 | |
| Additional FireInspections | ||
| | If the Fire Inspector must inspect premises asecondtime | |
| to ensure compliance with the Code an additional fee of | ||
| $50.00. |
-
If the Fire Inspector must inspect premises a third time to ensure compliance with the Code an additional fee of $100.00.
-
If the Fire Inspector must inspect premises a fourth time to ensure compliance with the Code an additional fee of $150.00.
| In the event of non-compliance with the Fire Inspector's | In the event of non-compliance with the Fire Inspector's | In the event of non-compliance with the Fire Inspector's | In the event of non-compliance with the Fire Inspector's | ||
|---|---|---|---|---|---|
| recommendations after a fourth visit the property owner is | recommendations after a fourth visit the property owner is | ||||
| subject to fines and expenses imposed by the Village Justice | |||||
| Court as per Village Code | Court as per Village Code | ||||
| §95. | |||||
| $100.00 for Residential | |||||
| Roof Repair / Replacement | See AttachedRoofing Permit Fee | No change | |||
| Schedule For Commercial Structures | |||||
| Oil Tank Abandonment/ | |||||
| Replacement | $100.00 | No change | |||
| (inside or underground) |
Page 4 of 12
Date Adopted: XX, YY 2026
| Type | Prior Fee | Proposed Fee | Notes |
|---|---|---|---|
| Planning Board: | |||
| SITE PLAN REVIEW | $200.00 w/SEAF; | ||
| $300.00 w/FEAF | $250.00 w/SEAF; | ||
| $350.00 w/FEAF | Receipts reviewed at meeting | ||
| for completeness | |||
| Planning Board: | |||
| MINOR SUBDIVISION | |||
| & | |||
| Planning Board: | |||
| MAJOR SUBDIVISION | $300.00 w/FEAF | ||
| plus $150.00/lot | $300.00 w/SEAF or FEAF | ||
| plus $150.00/lot | See NYS Village Law§7-728 | ||
| Planning Board: | |||
| LOT LINE ADJUSTMENT | $200.00 w/SEAF | No change | |
| Zoning Board: | |||
| AREA VARIANCE | $200.00 | $250.00 | All required mailingsare the |
| responsibility of theapplicant. | |||
| Receiptsrequired. | |||
| Zoning Board: | |||
| USE VARIANCE | $200.00 | $500.00 | All required mailingsare the |
| responsibility of theapplicant. | |||
| Receiptsrequired. | |||
| Zoning Board: | |||
| INTERPRETATION | $150.00 | $200.00 |
Page 5 of 12
Date Adopted: XX, YY 2026
==> picture [636 x 470] intentionally omitted <==
----- Start of picture text -----
SEQRA: SEAF $200.00 No change SEQRA: FEAF $300.00 No change ESCROW MAY BE REQUESTED BY PLANNING BOARD & ZONING BOARD OF APPEALS AS PER VILLAGE OF RED HOOK ZONING § 200-54 Sewer Department (Village Code § 145) Type Prior Fee Proposed Fee Notes Special Invoicing 3% of invoice Administrative Fee Included in Utility Bill Sewer Capital Fee $179.00 per EDU per quarter No change (quarterly) Sewer Rent/Use Fee Included in Utility Bill (Operation & $162.00 per EDU per quarter No change (quarterly) Maintenance) Resolution 5-2026 Sewerage Surcharge/ Volume Charge None listed TBD ( § 145-117) Capacity Charge None listed TBD See below ‘ Water Locate Water/Sewer Lines None listed Department ’ fees Locate Electric Service See below ‘ Water Lines beyond Utility None listed ’ Department fees = Responsibility Date Adopted: XX, YY 2026 Page 6 of 12 ----- End of picture text -----
| Type | Prior Fee | Proposed Fee | Notes |
|---|---|---|---|
| SewerLateral Permit | |||
| Application | |||
| (§145-31) | None listed | $100.00 application fee plus | |
| Equipment fees calculated by | |||
| Village Engineer | Paid to Building Department | ||
| SewerConnection Charge | |||
| (Tap Fee) | |||
| (§145-51-52) | None listed | Equipment & Labor costs | |
| calculated by Village Engineer | |||
| Dumping Fee | |||
| (§145-123) | None listed | TBD | |
| Wastewater Discharge | |||
| Permit–Industrial Use | |||
| (§145-70) | None listed | TBD | |
| Pretreatment Program | |||
| (§145-122) | None listed | TBD | |
| Administrative Fine | |||
| (§145-98) | ≤$1,000 per violation per day | No change | |
| Abnormal Sewage Fee | |||
| (§145-117) | None listed | TBD | |
| Excess Grease Trap | |||
| Maintenance Fee | Sewer O&M fee includes three (3) | ||
| pump outs per calendar year. All | |||
| additional $194.00/1,000 gal | Sewer O&M fee includes three | ||
| (3) pump outs per calendar | |||
| year. All additional | |||
| $214.00/1,000 gal | Fee added to Utility Bill | ||
| (quarterly) |
Page 7 of 12
Date Adopted: XX, YY 2026
Water Department (Village Code § 195)
See §195-26 and below
|Seeee §195-26
| and below | |||
|---|---|---|---|
| Type | Prior Fee | Proposed Fee | Notes |
| SpecialInvoicing | |||
| Administrative Fee | 3% of invoice | ||
| Damaged/Frozen Meter | |||
| (§195-5) | $50.00inspection feeplus cost of | ||
| replacement equipment | No change | ||
| Non-Metered Water | |||
| Service | |||
| (§195-6) | None listed | $500.00 per quarter | |
| Hydrant Use Application | None listed | $20.00 | Construction or non- |
| construction use | |||
| Hydrant Use: Meter Rental | |||
| & Use | None listed | $1,500.00 deposit, plus | |
| $100.00 per day, plus | |||
| $0.012 per gallon used | Deposit refundable upon | ||
| meter return. | |||
| FinalServiceRead/Bill | $50.00 | No change | Request at least 5 business |
| days before the closing/move | |||
| outdate | |||
| Fire Flow Evaluation | None listed | $130.00 | |
| Locate Water/Sewer Lines | None listed | $50.00 | Fee waived in the case of a |
| utility locating service request | |||
| (e.g.,DigSafe/UDig NY) |
Page 8 of 12
Date Adopted: XX, YY 2026
| Type | Prior Fee | Proposed Fee | Notes | |
|---|---|---|---|---|
| Locate Electric Service | ||||
| Lines beyond Utility | None listed | $250.00 | ||
| Responsibility | ||||
| $50.00 | ||||
| Service Turn on/off | $100.00(Emergency event [outside | No change | Feeforeach event | |
| of business hours]) | ||||
| $2,600.00* | ||||
| (with road cutting/crossing inv | ||||
| Tapping Fee | $2,500.00* | |||
| (with road cutting/crossing involvem | ||||
| ent,+$500) (within sidewalk, +$500) | olvement,+$500) (within sidew | |||
| alk, +$500) | ||||
| (withinState road, +$1,000 | ||||
| per lane). Additional charge | ||||
| for water service lines >3/4 | ||||
| inch | ||||
| $50.00 | ||||
| Service Turn on/off | $100.00 (Emergency event [outside | No change | For each event | |
| of business hours]) | ||||
| Police Department | ||||
| Type | ||||
| Prior Fee | ||||
| Proposed Fee | ||||
| Notes | ||||
| Fingerprinting | ||||
| $20.00 | ||||
| $25.00 | ||||
| Paid to Village Clerk | ||||
| Copy of Police Report | ||||
| None listed | ||||
| $0.25 per page | ||||
| Paid to Village Clerk | ||||
|Date Adopted: XX, YY 2026||||Page9of12|
|Village
| Clerk | |||
|---|---|---|---|
| Type | Prior Fee | Proposed Fee | Notes |
| Copies | None listed | $0.25 per page | |
| Returned/Bounced Check | None listed | $25.00 | |
| FOIL Fees | None listed | Copies = $0.25 perpage | |
| - | - | Storage device/media = | |
| - | - | $4.00 each | |
| - | - | If preparation requires >2 | |
| - | - | hours, hourly salary | |
| - | - | attributed to the lowest | |
| - | - | paid agency employee who | |
| - | - | has the necessary skill | |
| - | - | required to prepare a copy | |
| - | - | of the requested record(s). | |
| Birth/Death Certificate | $10.00 per Certificate or | ||
| No Record Certification | No change | ||
| Yard/GarageSale Permit | |||
| (§119) | $5.00 | No change | |
| EV Charging (ChargePoint | |||
| Station in Municipal Lot) | $0.12/kWh | No change | Additional ChargePoint fees |
| may apply. |
Page 10 of 12
Date Adopted: XX, YY 2026
Property Maintenance
| Property Maintenanceperty Maintenanceerty Maintenancey Maintenance Maintenance | |||
|---|---|---|---|
| Type | Prior Fee | Proposed Fee | Notes |
| Property Maintenance | |||
| (lawn mowing, weed | |||
| trimming) | None listed | $100.00 per hour, 1-hour | |
| minimum. $200.00 per hour | |||
| for second calendar year (CY) | |||
| offense, | |||
| $300.00 per hour for third CY | |||
| offense | Fees billed to property owner. | ||
| All unpaid feesre-leviedon | |||
| Village property taxesin April. | |||
| Sidewalk Snow/Ice | First offense in a season - | No change | Fees billed to property owner. |
| Removal | $2.00/linear foot, sanding/salting | - | All unpaid feesre-leviedon |
| - | $0.50/linear foot | - | Village property taxesin April. |
| - | Second offense - $3.00/linear foot, | - | - |
| - | sanding/salting $0.75/linear foot | - | - |
| - | Third and any subsequent offences - | - | - |
| - | $4.00/linear foot, sanding/salting | - | - |
| - | $1.00/linear foot | - | - |
| Trash Removal | None listed | $200.00 per hour, 1-hour | |
| minimum, per laborer plus | |||
| tipping fees | Fees billed to property owner. | ||
| All unpaid feesre-leviedon | |||
| Village property taxesin April. |
Page 11 of 12
Date Adopted: XX, YY 2026
Waste Management (Village Code §160 )
| Type | Prior Fee | Proposed Fee | Notes |
|---|---|---|---|
| Garbage Tags | Blue Tag (small bag), $3.00* each | Blue Tag (small bag), $3.50* | Small = 13 gal, typically white |
| - | Red Tag (large bag), $6.00* each | each | kitchen bag |
| - | - | Red Tag (large bag), $7.00* | Large = 30 gal, typically black |
| - | - | each | trash bag |
| - | - | - | Tags available from Village |
| - | - | - | Clerk, Red Hook Public Library, |
| - | - | - | and Taste Budd’s*. |
| - | - | - | *additional convenience fee |
| - | - | - | may apply |
| Bags in Bulk Pickup | $75.00for up to 25 bags or | ||
| $125.00 for up to 50 bags | |||
| (30 gal bags) | No change | ContactVillage Clerk to set up | |
| and pay for service | |||
| Oversized Items(e.g., | |||
| mattress, furniture, table, | |||
| chair, rug) | $25.00 (additional $10.00 for | ||
| mattresses & box springs) | No change | Tags available from Village | |
| Clerk | |||
| Scrap Metal Collection | Free | No change | Contact Village Clerkor DPW |
| to schedule. |
Page 12 of 12
Date Adopted: XX, YY 2026