RESOLUTION TO AUTHORIZE FINAL ARPA FUNDING
Resolution #15-2025 — 2025-04-24
WHEREAS
- the Village of Red Hook has a final report to account for the remaining ARPA funding expenditures
- the Board acknowledges that some of the previously approved items have come in at costs less than allocated, which results in an amount of $5,205.44 available to fund other items/projects already purchased or completed prior to December 31, 2024
RESOLVED
- that the Village Board of Trustees authorizes the following 2024 costs to be covered by the remaining ARPA funds to the extent funds are available: WWTP Capacity Upgrade and Collection System Expansion – work thru August 2024 - $6,340