Red Hook WatchIndependent Community Resource

Appendix K: Cost Estimates

1 versions2024-06-10attached document

Versions

  1. 12024-06-10
    attached document

Document

Appendix K Cost Estimates

Project Name: Village of Red Hook WWTP

Project# : 23-2861 Date: 6/5/2024 Prepared By: R. Flores

==> picture [99 x 62] intentionally omitted <==

Delaware Engineering, D.P.C.

Conceptual Cost Opinion Phase 2 Collection System

Conceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection System
IDDescriptionQuantityUnitsMaterialsLaborUnit CostTotal Unit CostSubtotals
1Services
1.14" GravityPVC Sewers2000LF$60.00$20.00$80.00$160,000.00
1.21250-Gallon ST112EA$7,000.00$3,000.00$10,000.00$1,120,000.00
1.32500-Gallon ST25EA$9,000.00$3,000.00$12,000.00$300,000.00
1.43000-Gallon ST5EA$11,000.00$5,000.00$16,000.00$80,000.00
1.55000-Gallon ST3EA$15,000.00$5,000.00$20,000.00$60,000.00
1.6Greast Trap4EA$10,000.00$5,000.00$15,000.00$60,000.00
1.71.5" Lateral Pipe8000LF$30.00$20.00$50.00$400,000.00
1.8Lateral Connections145EA$600.00$200.00$800.00$116,000.00
1.9Shut off with Check Valve145EA$1,250.00$300.00$1,550.00$224,750.00
$2,520,750.00
2Sewers
2.12" HDPE FM11100LF$42.00$20.00$62.00$688,200.00
2.23" HDPE FM5400LF$48.00$20.00$68.00$367,200.00
2.34" HDPE FM4400LF$60.00$20.00$80.00$352,000.00
2.46" HDPE FM1250LF$80.00$30.00$110.00$137,500.00
$1,544,900.00
3Manholes
3.1Air/Vaccuum Relief MH10EA$8,000.00$3,000.00$11,000.00$110,000.00
3.2FlushingConnections20EA$1,700.00$3,000.00$4,700.00$94,000.00
$204,000.00
4Pumps
4.1Simplex Pumps112EA$4,000.00$1,000.00$5,000.00$560,000.00
4.2Duplex Pumps32EA$10,000.00$2,000.00$12,000.00$384,000.00
4.3Electrical145EA$2,000.00$2,000.00$4,000.00$580,000.00
4.4Spare Parts1LS$75,000.00$75,000.00$75,000.00
$1,599,000.00
5Site Work
5.1Asphalt Driveways1LS$100,000.00$100,000.00$200,000.00$200,000.00
5.2Gravel Driveways1LS$50,000.00$50,000.00$100,000.00$100,000.00
5.3TopSoil and Seed1LS$100,000.00$100,000.00$200,000.00$200,000.00
5.4Test Pits150EA$500.00$500.00$1,000.00$150,000.00
$650,000.00

Project Name: Village of Red Hook WWTP Project# : 23-2861 Date: 6/5/2024 Prepared By: R. Flores

==> picture [99 x 62] intentionally omitted <==

Delaware Engineering, D.P.C.

Conceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection SystemConceptual Cost Opinion Phase 2 Collection System
IDDescriptionQuantityUnitsMaterialsLaborUnit CostTotal Unit CostSubtotals
6General Condition
6.1Insurance & Bonds1LS$100,000.00$100,000.00$100,000.00
6.2Mobilization1LS$100,000.00$100,000.00$100,000.00
6.3PM & General Condition1LS$250,000.00$250,000.00$250,000.00
$450,000.00
Cost Summary
2024 Construction Cost Subtotal
2026 Construction Cost Subtotal (8% increase/year)
15% Engineering
20% Contingancy
Project Costs
$6,968,650.00
8,128,000.00
$
1,219,200.00
$
1,625,600.00
$
10,972,800.00
$

Project Name: Village of Red Hook WWTP

Project# : 23-2861 Date: 6/5/2024 Prepared By: R. Flores

==> picture [99 x 62] intentionally omitted <==

Delaware Engineering, D.P.C.

Conceptual Cost Opinion Upgrade Existing WWTP by adding 190,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 190,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 190,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 190,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 190,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 190,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 190,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 190,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 190,000 GPD MBR
IDDescriptionQuantityUnitsMaterialsLaborUnit CostTotal Unit CostSubtotals
1Packaged MBR with UV
1.1170,000gpd MBR Plant1LS$1,300,000.00$50,000.00$1,350,000.00$1,350,000.00
1.2Start Up1LS$10,000.00$20,000.00$30,000.00$30,000.00
1.3Excavation,fill,backfill133CY$25.00$25.00$50.00$6,666.67
1.4Concrete Slab44CY$1,200.00$1,300.00$2,500.00$111,111.11
$1,497,777.78
2Concrete Tanks
2.150,000 Gal EQTank Walls86CY$1,200.00$1,800.00$3,000.00$256,666.67
2.240,000 Gal Sludge Tank Walls54CY$1,200.00$1,800.00$3,000.00$163,333.33
2.345,000 Gal Aeration Tank Walls54CY$1,200.00$1,800.00$3,000.00$163,333.33
2.4Excavation,fill,backfill1111CY$25.00$25.00$50.00$55,555.56
2.5Common Concrete Slab74CY$1,200.00$1,300.00$2,500.00$185,185.19
$824,074.07
3Yard Piping& Site Work
3.1Yard Piping1LS$100,000.00$50,000.00$150,000.00$150,000.00
3.2Sie Work1LS$30,000.00$60,000.00$90,000.00$90,000.00
$240,000.00
4Electrical Work
4.1Site Electical1LS$100,000.00$50,000.00$150,000.00$150,000.00
4.2Equipment Electrical1LS$50,000.00$50,000.00$100,000.00$100,000.00
4.3Gear1LS$10,000.00$10,000.00$20,000.00$20,000.00
4.4Generator and ATS1LS$60,000.00$25,000.00$85,000.00$85,000.00
4.5Controls1LS$10,000.00$10,000.00$20,000.00$20,000.00
$375,000.00
5General Condition
5.1Insurance & Bonds1LS$60,000.00$60,000.00$60,000.00
5.2Mobilization1LS$10,000.00$50,000.00$60,000.00$60,000.00
5.3PM & General Condition1LS$450,000.00$450,000.00$450,000.00
$570,000.00
Cost Summary

2024 Construction Cost Subtotal $3,506,851.85

Project Name: Village of Red Hook WWTP Project# : 23-2861 Date: 6/5/2024 Prepared By: R. Flores

==> picture [99 x 62] intentionally omitted <==

Delaware Engineering, D.P.C.

Conceptual Cost Opinion Upgrade Existing WWTP by adding 190,000 GPD MBR

IDDescriptionQuantityUnitsMaterialsLaborUnit CostTotal Unit CostSubtotals
2026 Construction Cost Subtotal (8% increase/year)
15% Engineering
20% Contingancy
Project Costs4,090,000.00
$
550,000.00
$
818,000.00
$
5,458,000.00
$

Project Name: Village of Red Hook WWTP

Project# : 23-2861 Date: 6/5/2024 Prepared By: R. Flores

==> picture [99 x 62] intentionally omitted <==

Delaware Engineering, D.P.C.

Conceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBR

Conceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBR
IDDescriptionQuantityUnitsMaterialsLaborUnit CostTotal Unit CostSubtotals
1Packaged MBR with UV
1.1250,000gpd MBR Plant1LS$2,700,000.00$100,000.00$2,800,000.00$2,800,000.00
1.2Start Up1LS$10,000.00$20,000.00$30,000.00$30,000.00
1.3Excavation,fill,backfill889CY$25.00$25.00$50.00$44,444.44
1.4Concrete63CY$1,200.00$1,300.00$2,500.00$157,407.41
$3,031,851.85
2Concrete Tanks
2.185,000 Gal EQTank Walls113CY$1,200.00$1,800.00$3,000.00$338,333.33
2.390,000 Gal Aeration Tank Walls86CY$1,200.00$1,800.00$3,000.00$256,666.67
2.4Excavation,fill,backfill1389CY$25.00$25.00$50.00$69,444.44
2.5Common Concrete Slab148CY$1,200.00$1,300.00$2,500.00$370,370.37
$1,034,814.81
3Convert EA to Sludge HoldingTanks
3.1Demo1LS$20,000.00$60,000.00$80,000.00$80,000.00
3.2Piping1LS$10,000.00$30,000.00$40,000.00$40,000.00
$120,000.00
4Yard Piping& Site Work
3.1Yard Piping1LS$120,000.00$60,000.00$180,000.00$180,000.00
3.2Sie Work1LS$40,000.00$80,000.00$120,000.00$120,000.00
$300,000.00
5Electrical Work
4.1Site Electical1LS$100,000.00$50,000.00$150,000.00$150,000.00
4.2Equipment Electrical1LS$60,000.00$60,000.00$120,000.00$120,000.00
4.3Gear1LS$10,000.00$10,000.00$20,000.00$20,000.00
4.4Generator and ATS1LS$80,000.00$30,000.00$110,000.00$110,000.00
4.5Controls1LS$15,000.00$15,000.00$30,000.00$30,000.00
$430,000.00
6General Condition
5.1Insurance & Bonds1LS$80,000.00$80,000.00$80,000.00
5.2Mobilization1LS$10,000.00$50,000.00$60,000.00$60,000.00
5.3PM & General Condition1LS$550,000.00$550,000.00$550,000.00
$690,000.00
Cost Summary

Project Name: Village of Red Hook WWTP Project# : 23-2861 Date: 6/5/2024 Prepared By: R. Flores

==> picture [99 x 62] intentionally omitted <==

Delaware Engineering, D.P.C.

Conceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 250,000 GPD MBR
IDDescriptionQuantityUnitsMaterialsLaborUnit CostTotal Unit CostSubtotals
2024 Construction Cost Subtotal
2026 Construction Cost Subtotal (8% increase/year)
15% Engineering
20% Contingancy
Project Costs
$5,486,666.67
6,400,000.00
$
850,000.00
$
1,280,000.00
$
8,530,000.00
$

Project Name: Village of Red Hook WWTP

Project# : 23-2861 Date: 6/5/2024 Prepared By: R. Flores

==> picture [99 x 62] intentionally omitted <==

Delaware Engineering, D.P.C.

Conceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBR

Conceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBR
IDDescriptionQuantityUnitsMaterialsLaborUnit CostTotal Unit CostSubtotals
1Packaged MBR with UV
1.1250,000gpd MBR Plant3LS$2,700,000.00$100,000.00$2,800,000.00$8,400,000.00
1.2Start Up3LS$10,000.00$20,000.00$30,000.00$90,000.00
1.3Excavation,fill,backfill2667CY$25.00$25.00$50.00$133,333.33
1.4Concrete189CY$1,200.00$1,300.00$2,500.00$472,222.22
$9,095,555.56
2Concrete Tanks
2.185,000 Gal EQTank Walls338CY$1,200.00$1,800.00$3,000.00$1,015,000.00
2.390,000 Gal Aeration Tank Walls257CY$1,200.00$1,800.00$3,000.00$770,000.00
2.4Excavation,fill,backfill4167CY$25.00$25.00$50.00$208,333.33
2.5Common Concrete Slab444CY$1,200.00$1,300.00$2,500.00$1,111,111.11
$3,104,444.44
3Convert EA to Sludge HoldingTanks
3.1Demo2LS$20,000.00$60,000.00$80,000.00$160,000.00
3.2Piping2LS$10,000.00$30,000.00$40,000.00$80,000.00
$240,000.00
4Yard Piping& Site Work
3.1Yard Piping3LS$120,000.00$60,000.00$180,000.00$540,000.00
3.2Sie Work3LS$40,000.00$80,000.00$120,000.00$360,000.00
$900,000.00
5Electrical Work
4.1Site Electical3LS$100,000.00$50,000.00$150,000.00$450,000.00
4.2Equipment Electrical3LS$60,000.00$60,000.00$120,000.00$360,000.00
4.3Gear3LS$10,000.00$10,000.00$20,000.00$60,000.00
4.4Generator and ATS3LS$80,000.00$30,000.00$110,000.00$330,000.00
4.5Controls3LS$15,000.00$15,000.00$30,000.00$90,000.00
$1,290,000.00
6General Condition
5.1Insurance & Bonds3LS$80,000.00$80,000.00$240,000.00
5.2Mobilization3LS$10,000.00$50,000.00$60,000.00$180,000.00
5.3PM & General Condition3LS$550,000.00$550,000.00$1,650,000.00
$2,070,000.00
Cost Summary

Project Name: Village of Red Hook WWTP Project# : 23-2861 Date: 6/5/2024 Prepared By: R. Flores

==> picture [99 x 62] intentionally omitted <==

Delaware Engineering, D.P.C.

Conceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBRConceptual Cost Opinion Upgrade Existing WWTP by adding 750,000 GPD MBR
IDDescriptionQuantityUnitsMaterialsLaborUnit CostTotal Unit CostSubtotals
2024 Construction Cost Subtotal
2026 Construction Cost Subtotal (8% increase/year)
15% Engineering
20% Contingancy
Project Costs
$16,460,000.00
19,199,000.00
$
3,000,000.00
$
3,839,800.00
$
26,038,800.00
$

Proposed for inclusion in

This document was circulated as a possible addition to:

Referenced by

These other documents cite or incorporate this one: