WIIA Grant Project Construction Change Orders and Directives

Meetings/Resolutions/(operational)
One-time (complete)operationalone_timeApprove multiple construction change orders and work change directives for WIIA grant projects with corrected dates and exact dollar amounts.
First seen
2024-10-24
Latest event
2024-10-24
adopted
Expires

Resolution text

RESOLVED

  1. Construction Change Order No. 1, Work Change Directive No. 1, Work Change Directive No. 2, and Work Change Directive No. 3 are approved.

Document references

Cites or incorporates

Lifecycle (1 event)

2024-10-24adoptedvote: unanimous
Approve Construction Change Order No. 1, Work Change Directive No. 1, Work Change Directive No. 2, and Work Change Directive No. 3 related to WIIA grant projects.
moved by Bradley-Rickard · seconded by Appenzeller
Show text snapshot for this event
Resolved
  1. Construction Change Order No. 1, Work Change Directive No. 1, Work Change Directive No. 2, and Work Change Directive No. 3 are approved.
Subject key: wiia_grant_project_change_orders