Red Hook Infrastructure – Sewer Project Monthly Report — September 2023

1 versions2023-10-10attached document

Document

Village of Red Hook Red Hook Infrastructure – Sewer Project Monthly Report September 2023

Red Hook Sewer Project

Substantial Completion was achieved on March 30, 2023. Restoration & Punch List remain to be completed prior to Final Completion being achieved.

Electrical Contract:

  1. Propane tank at WWTP site- schedule start-up training session – scheduled for the week of 9/11/23. Completed

  2. Install roof on control panel structure. Work started 10/3 – should be finished by 10/6.

General Contract:

Final property restoration punch list being worked on the week of 10/9.

1.Perform final inspection of each STEP control panel, fix any issues with electrical seals, etc. Carver shall provide a letter stating that they have performed the required final inspection of each control panel.

  1. Provide final spare STEP pump as part of spare parts list. All other spare parts have been delivered.

  2. Provide required O&M Manuals. Due to be delivered by end of October

  3. Provide record drawing per specification Section 017700.1.5.F. Due to be delivered by end of October

  4. Provide photographic documentation (pre and post work) per Section 013223. Due to be delivered by end of October

FINANCING

With Form E #11, we have expended $7,819,980.90. That leaves $627,137.10 the majority of which is retainage. Nothing further expended to date.