Village of Red Hook Water Treatment Facilities Monthly Report — March 2025

1 versions2025-04-14attached document

Document

Village of Red Hook Water Treatment Facilities Monthly Report

April 9, 2025

System Flow

During the month of March the water treatment facility treated 7,893,291 total gallons, which is an average of 254,622 gallons per day. See below for the Annual Daily Average Flow Chart:

All bacteriological samples for the month were collected and transported to York Analytical, Newton, Connecticut. Please see below for sample locations and results:

LocationTotal ColiformE. Coli
7329 S. BroadwayAbsentAbsent
2 W. Market St.AbsentAbsent
7331 S. BroadwayAbsentAbsent

Chemical Usage

During the month of March 2025, the water treatment plant used 75 gallons of sodium hypochlorite. The average daily use was 2.41 gallons per day.

If you should have any questions in regards to this report, please feel free to reach out to me at our main office at (845) 244-0129 or by email at Fernando@C3NDEnviro.com

Sincerely,

Fernando Dongo Principal Consultant C3ND Environmental Consulting

0

Village of Red Hook Water Treatment 7467 South Broadway, Red Hook, New York 12571

==> picture [38 x 6] intentionally omitted <==

----- Start of picture text -----

04/01/2025 ----- End of picture text -----

==> picture [416 x 135] intentionally omitted <==

----- Start of picture text -----

Water System Water System Notes: Monthly Total Coliform All results absent for the month Deficiencies Town/Village Interconnect 2020 test indicated this was not a viable option for Village flow in case of emergency. Engineering review currently in place. ----- End of picture text -----

==> picture [49 x 6] intentionally omitted <==

----- Start of picture text -----

For Future Notes: ----- End of picture text -----