Village of Red Hook Water Treatment Facilities and Water Systems Operation Report — December 2024

1 versions2025-01-13attached document

Document

Village of Red Hook Water Treatment Facilities Monthly Report

January 1, 2025

System Flow

During the month of December the water treatment facility treated 7,594,809 total gallons, which is an average of 244,994 gallons per day. See below for the Annual Daily Average Flow Chart:

All bacteriological samples for the month were collected and transported to York Analytical, Newton, Connecticut. Please see below for sample locations and results:

LocationTotal ColiformE. Coli
Traditions Mail RoomAbsentAbsent
53 ElizabethAbsentAbsent
29 E. MarketAbsentAbsent

Chemical Usage

During the month of December, the water treatment plant used 75 gallons of sodium hypochlorite. The average daily use was 2.4 gallons per day.

If you should have any questions in regards to this report, please feel free to reach out to me at our main office at (845) 244-0129 or by email at Fernando@C3NDEnviro.com

Sincerely, Fernando Dongo Principal Consultant C3ND Environmental Consulting