Red Hook WatchIndependent Community Resource

Avanti Control Systems Proposal — HACH Chlorine Analyzer

1 versions2024-10-17attached document

Versions

  1. 12024-10-17

Document

==> picture [171 x 65] intentionally omitted <==

Proposal

Date: 08/07/2024 Quote Number: 24Q112 Company: Village Red Hook Sent To: Ablen Amrod Phone No.: (845) 399-4028 Fax Number: Email: aamrod@delawareengineering.com From: Timothy Tesiero (ttesiero@acsautomate.com) Re : HACH Chlorine Analyzer Proposal

==> picture [88 x 79] intentionally omitted <==

This proposal is based on the following specifications and drawings:

Specification: N/A Dated: N/A Revisions: N/A Drawings: N/A Dated: N/A Revisions: N/A

Addenda

None

Revision History None

Qualifications:

Field Site Engineer: Timothy M. Tesiero

==> picture [62 x 22] intentionally omitted <==

Certification # PF400-1004-294

Member No. 33228383

==> picture [52 x 26] intentionally omitted <==

Industrial Control Panels 508A Certification # NITW.E353063 Industrial Control Panels Certified for Canada Certification # NITW7.E353063 Industrial Control Panels Relating to Hazardous Locations Certification # NRBX.E4664268

Accordingly, our price will include:

Avanti Control System Inc. 204 County Hwy 157 Gloversville, New York 12078 Ph: (518) 921-4368 Fax: (518) 921-4486 “Your Automation Solutions Partner”

==> picture [171 x 65] intentionally omitted <==

| Service | Unit Price | Ext. Price | | Qty – 1 | $3,367.75 | $3,367.75 | | HACH 857280 | $3,191.05 | $3,191.05 | | CL17sc Colorimetric Chlorine Analyzer with Standpipe | $ 138.70 | $ 277.40 | | Installation Kit and Reagents for Total Chlorine | $ 23.04 | $ 23.04 | | Qty – 1 | $ 72.53 | $ 72.53 | | HACH LXV525.99A11551 | $ 1,039.77 | $1,039.77 | | SC4500 Controller, Prognosys, 5x mA Output, 2 digital | $ 1,000.00 | $1,000.00 | | Sensors, 100-240 VAC, without power cord. | - | $ 85.00 | | Standard lead time: 3 days. | - | $ 0.0 | | Qty – 2 | - | $ 9,056.54 | | HACH 8560400 CL17sc Tubing Kit (pre-assembled). | - | - | | Standard lead time: 3 days. | - | - | | Qty – 1 | - | - | | HACH 8573100 | - | - | | CL17sc Cell Cleaning Kit. Standard lead time: 3 days. | - | - | | Qty – 1 | - | - | | HACH 2556900 | - | - | | Free Chlorine Reagent Set for chlorine analyzer CL17/CL17sc. | - | - | | Standard lead time: 3 days. | - | - | | Qty – 1 | - | - | | Overhead and Profit @ 15% | - | - | | Qty – 1 | - | - | | Installation and Startup | - | - | | Includes Travel | - | - | | Shipping | - | - | | Sales Tax | - | - | | Total | - | - |

Prices do NOT include:

Specialty Insurances (Builders Risks, Bonding, Environmental etc.) Digging, Trenching, or Excavation work Core Drilling Painting Concrete Repair of Any Kind Asbestos work or any other hazardous work NYS Sales or Use Taxes Additional Travel Overtime or Premium Time Holidays

Notes and Clarifications

All equipment being serviced must be accessible from the ground. Any equipment requiring fall protection, ladders, scaffolding, or installation in confined spaces requires advanced notice. This proposal does not include field service rates for these areas and will have to be re-quoted as such.

Avanti Control System Inc. 204 County Hwy 157 Gloversville, New York 12078 Ph: (518) 921-4368 Fax: (518) 921-4486 “Your Automation Solutions Partner”

==> picture [171 x 65] intentionally omitted <==

Validation flow meters verify flow rates. Ultrasonic sensors are mounted on the external side of the pipe. To achieve 100% sensor signal strength, paint, grease, and dirt are removed down to bare surfaces. It’s the customer's responsibility to repaint all surfaces.

Exceptions to Specifications:

Options Priced Individually Above

Warranty:

None

Options:

None

Delivery:

  • TBD

  • This proposal is valid for 30 days from the date of quotation.

Invoicing:

NET 15

Note: All Invoices not paid by the due date will be subjected to 1.5% monthly 18% per annum

Alterations/Changes:

Any alteration or change from the specifications as detailed above involving extra costs will be effectual only upon written order and will be over and above the quoted price.

Attachments:

2023 Field Rate Schedule

Standard Terms and Conditions:

  • Customer agrees with Avanti Control Systems, Inc., to proceed with work by issuing a purchase order.

  • Customer agrees to “Invoicing” as outlined above with progression terms as stated by the issuance of a

  • purchase order.

  • Customer agrees to late fee penalties per invoice past the due dates unless otherwise in which special terms

  • have been outlined in this proposal.

  • Customer agrees to all labor rates as listed above

Document Confidentiality Statement

Avanti Control System Inc. 204 County Hwy 157 Gloversville, New York 12078 Ph: (518) 921-4368 Fax: (518) 921-4486

“Your Automation Solutions Partner”

==> picture [171 x 65] intentionally omitted <==

The information in this document is confidential to the person it addresses and should not be disclosed to anyone else. It may not be reproduced in whole or in part, nor may any of the information contained therein be disclosed without the prior consent of the directors of Avanti Control Systems, Inc. (‘the Company’). A recipient may not solicit, directly or indirectly (whether through an agent or otherwise), the participation of another institution or person without the prior approval of the directors of the Company.

The contents of this document have not been independently verified, and they do not purport to be comprehensive or to contain all the information that a prospective investor may need. No representation, warranty, or undertaking, expressed or implied, will be made or given. No responsibility or liability is or will be accepted by the Company or any of its directors, employees, or advisors concerning the accuracy or completeness of this document or any other written or oral information made available in connection with the Company.

Any reproduction, dissemination, copying, disclosure, modification, distribution, or publication of this material is strictly prohibited.

Thank you again for the opportunity to provide this proposal; after reviewing our proposal, should you have any questions, please do not hesitate to contact me. Thank you

Thank you again for the opportunity to provide this proposal; after reviewing our proposal, should you have any questions, please do not hesitate to contact me. Thank you.

Sincerely, Avanti Control Systems, Inc. Timothy Tesiero Timothy M. Tesiero

Avanti Control System Inc. 204 County Hwy 157 Gloversville, New York 12078 Ph: (518) 921-4368 Fax: (518) 921-4486 “Your Automation Solutions Partner”

Changes between versions

2025-04-102025-04-14
substantive change+434

The document was significantly truncated, removing all reports for the Village Green Committee and Climate Smart Communities, and focusing solely on the Sewer Department and other remaining sections.

  • Title changed from 'Village of Red Hook Monthly Reports — March 2025' to 'Sewer Department Report — March 2025'
  • Document date advanced from 2025-04-10 to 2025-04-14
  • Removed 'Village of Red Hook Village Green Committee Monthly Report March 2025'
  • Removed 'Village of Red Hook Climate Smart Communities Monthly Report March 2025'
Show red-line diff
Village of Red Hook Village Green Committee Monthly Report March 2025 Planting is almost here - scheduled for April 19. This last month we secured our final spots for the Spring Planting. The committee canvassed and did outreach to our residents trying to recruit some new members to the committee and are all set for our next meeting which will address our preparation for planting day itself and other goals for the year. A reminder that the Village Green meets once a quarter and works on diversifying our tree canopy and is working toward providing helpful information to our residents about how to protect their own trees. Two representatives from VGC went to the annual Tree Cities luncheon where we were honored in our 23rd year. The DEC gave a presentation on the governor's 25 Million Tree planting effort. The Town is already promoting the use of the DEC's Tree Tracker so that would be a fun thing for the Village to work on and could be a great project for the upcoming year. Any tree planted since January 2024 can be counted. The goal is 25 million by 2033. We are actively recruiting members. If you are interested in giving back to your community but don ’t have a lot of time to give this may be the perfect committee for you! Please contact me or Jen Cavanaugh, the Clerk. Village of Red Hook Sewer Department Monthly Report March 2025 In March, there were some strides and setbacks with the operating of the plant. The Village pressed the operator to send copies of all Notices of Violations, where necessary. Remembering lab results are a month behind, a NOV was confirmed to be sent for the month of February - which happened before a calculated dump of mixed liquor was added to help engage the bugs. There were still mechanical issues in relation to the UV lights and so Chlorine treatment, a standard treatment process, was authorized to continue to be used in the tanks. Working through the to-do list - the crew was able to get the necessary tanks emptied and begin to start work on the list of necessary repairs that came out of the audit - as well as connect the EQ tank to the Odor Control system (which needed the ground to thaw). At the alternating meeting we discussed not moving forward with the RFP process and to shift into a new direction for the operation and maintenance of the WWTP. We continued to meet with our representative from the New York Rural Water Association who has experience with sewer code and functionality of WWTPs in general. In the month of March, the contract with C3ND, as our operator for both water and sewer, was terminated and as of March 31, 2025 the Village engaged Delaware Engineering, fully accredited/certified to operate WWTPs, as our operator. These actions were solidified at the Board s workshop at the end of March. As Delaware is familiar with the plant and with aiding and addressing malfunctioning plants - their goal is to break it down to brass tacks and start from scratch in learning what this particular system needs and how to get it up to snuff. Delaware worked on a plan to attack the plant with more testing (influent) to see if we are bringing something into the plant that is causing the uneven/unhealthy bug environment. Additionally, they were poised to go in on day 1 and do a full assessment of the plant itself. It is a priority to make sure we have a fully functional and operating WWTP. I also acknowledge that residents are duly concerned about the operations of the plant. It will take time, but I am trusting in the new team to whip the plant into shape so that after we can then move forward. The Sewer team meets every other Friday. If you have concerns, comments, etc. related to the WWTP or the Sewer Use Area please do not hesitate to reach out. Village of Red Hook Speed Limit Initiative Monthly Report March 2025 There hasn t been any new developments since the last meeting. Village of Red Hook Town of Red Hook Greenway and Trails Committee Monthly Report March 2025 The March meeting covered proposed road signage/safety measures for the Saw Kill Trail to alert drivers that there will be people on the road as the trail connects on and through the roads. There were some repair/maintenance updates such as repainting the sharrows and also adjusting the culvert bridge to accommodate tractors/mowers more easily, but both are weather dependent. The committee is actively working on promoting the trails as off-road and safer options for traveling between schools and neighborhoods and working through educational material to send out regarding the “ rules of the roads/trails ” such as road safety, looking both ways, walking against traffic, riding with traffic, etc. Upcoming dates: Ribbon Cutting event for Saw Kill Phase 2, by WLT will be held Saturday, April 26[th] at 1:30 so mark your calendars! It is in conjunction with the Rail to Trail Conservancy s National Trails Day! Village of Red Hook Climate Smart Communities Monthly Report March 2025 The CSC continues to meet monthly typically on the third Thursday of the month - however, in April due to Spring Break the committee will meet a week earlier (April 10th) at Village Hall, feel free to join us! We received updates on the RHHS compost program (currently only in their kitchens). We talked about the Village ’ s Compost program that will be launching later this spring. And as a quick refresher, we received a grant from the County to start a new food waste drop off/collection site. This will be a 24/7/365 food waste hub - meaning residents will have access to it whenever they want. Residents are urged to express interest now and once the program goes live, you can register for it. After residents register, they will be provided with instructions on how to move forward to officially be signed up with the Village ’ s compost program. Residents will receive complimentary countertop compost bins, while supplies last. And the Food Waste Hub/Drop off will be in the municipal lot. If you are interested in being informed about this new initiative, please reach out to myself or the Clerk ’ s office. A subcommittee of the CSC did some research into the Safe Routes to School program itself and what it entails and was happy to learn that the Village had already engaged with an engineer to work on speed limit and particularly a School Zone. We discussed an upcoming “ Tour de Red Hook ” that is being organized by the Red Hook Public Library - and could be a good chance to do some resident canvassing regarding bike/pedestrian use of roads to and around the schools. Additionally, it is a great opportunity to engage residents about the Safe Routes to School program. In the meantime, they are tasked next with compiling a list of action items to recommend to the Board for consideration prior to moving forward on action items for the CSC program. In March, I attended the CAC Roundtable event hosted by Dutchess County Planning and Development at Cornell Cooperative Extension ’ s Dutchess Campus and a few days later was at the 3rd annual Climate Summit held at SUNY Orange. Both provided great opportunities to discuss with experts in the areas and other municipalities what they are doing to address climate change and any hiccups they foresee along the way, especially with the current federal administration and funding concerns. Additionally meet with volunteers who are in similar taskforces/committees and the work they are doing within their committees/taskforce. CSC taskforce meetings are open to the public and we are actively recruiting members. If you are interested in joining the task force or just sitting in, feel free to reach out to me or check the Village ’ s Calendar for upcoming meetings. Our April meeting was moved forward a week due to Spring Break, so we just met; however, we meet the Third Thursday of the month at 4 p.m. at Village Hall - so the next meeting is scheduled for May 15th. Upcoming events of interest: Film Screening of _Legion_ Monday, April 21 @ 6:30 p.m. hosted by Sustainable Hudson Valley Repair Café - Saturday, April 26 @ RHCC Tour de Red Hook - Sunday, May 4th Drive Electric Vehicles Demo May 10th from 1-4 at the Red Hook Town Hall

Referenced by