VILLAGE OF RED HOOK — WATER SYSTEM SCADA UPGRADES PROJECT CONTRACT #1E — CONSTRUCTION CHANGE ORDER NO. 2
Owner ___ Village of Red Hook Date _ 3/24/24 Project ___Village of Red Hook — Water System SCADA Upgrades Project — Contract #1E Owner's Contract No. #1E Contractor: __[Avanti][Controls] Date of Contract Start _ October 17, 2023 You are directed to make the following changes in the Contract Documents: Reduce the contract value by the unused allowance amount of $6,730.96. Reason for Change Order: Unused Allowance.
Date _ 3/24/24
CONTRACT PRICE CONTRACT TIMES (Calendar Days) To Substantial Completion Original: $ 416,700.00 ORIGINAL: 250 days Previous C.O.s (ADD): ($_ 26,622.00) Previous C.O.s (ADD/DEDUCT): This C.O. (ADD / NTE): ($___ 6,730.96) This C.O. (ADD/DEDUCT): -0Contract Price with all REVISED: 250 days Approved Change Orders: $383,347.04 Notice to proceed: October 17, 2023 + 250days Original Completion Date: June 23, 2024 Revised Completion Date: June 23, 2024
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO,
==> picture [450 x 152] intentionally omitted <==
----- Start of picture text -----
RECOMMENDED: G C ' By: 3/24/25 Delaware Engineering D.P.C. (Authorized Signature) Date APPROVED: By: an Owner (Authorized Signature) Date byACCEPTED:re CA 3]25)z025 Contractor (Authorized Signature) Date ----- End of picture text -----