Village of Red Hook Red Hook Infrastructure — Sewer Project Monthly Report August 2023
Red Hook Sewer Project
Substantial Completion was achieved on March 30, 2023. Restoration & Punch List remain to be completed prior to Final Completion being achieved.
The following items are still outstanding:
Electrical Contract:
-
Propane tank at WWTP site- schedule start-up training session — scheduled for the week of 9/11/23.
-
Install roof on control panel structure.
General Contract:
1.Perform final inspection of each STEP control panel, fix any issues with electrical seals, etc. Carver shall provide a letter stating that they have performed the required final inspection of each control panel.
-
Provide final spare STEP pump as part of spare parts list. All other spare parts have been delivered.
-
Provide required O&M Manuals.
-
Provide record drawing per specification Section 017700.1.5.F.
-
Provide photographic documentation (pre and post work) per Section 013223.
FINANCING
USDA-RD $1.2MM grant is funding the last part of the project. We have now received funding to pay invoices from the USDA Form E #10. We have another distribution (Form E #11) expected later this week.
With Form E #11, we have expended $7,819,980.90. That leaves $627,137.10 the majority of which is retainage.