Village of Red Hook Red Hook Infrastructure – Sewer Project Monthly Report April 2023
1. Red Hook Sewer Project
Substantial Completion was achieved on March 30, 2023. Restoration & Punch List remained to be completed prior to Final Completion being achieved.
Progress meeting #34 was held on April 14, 2023, in the Red Hook Village
Building and via telephone conference call. Carver Construction (A.G. Bourgeois & Eric Klefbeck), C3ND (Fernando Dongo), and the Village of Red Hook (Karen Smythe) attended. Items discussed included:
-
Tasks Completed Since March 24, 2023:
-
Replacement tank set at 16 East Market (Delaware Engineering).
-
Eric to confirm if tank at 47 East Market is complete – vault needed to be replaced with correct size.
-
All tanks are up and running – except at the Soap Factory
-
Top soil placed throughout the Village. St. Paul’s Church remaining – should be complete today.
-
Top soil complaints from first batch of top soil – have gone back and added better top soil
-
Seed subcontractor started today (April 14).
-
Blacktop prep started yesterday (April 13).
-
Bollards installed around the UV unit, generator propane tank, and blowers at WWTP.
-
Transfer switch installed at the WWTP.
-
-
Tasks Scheduled:
Carver Construction – General Contractor:
-
Placing Blacktop to start Monday if no rain. Blacktopping should take @ 2 weeks.
-
Seed subcontractor should take 3-4 days. They started 4/14.
-
Redo sidewalks – 6 locations. Next week or after paving.
-
Sausto – Electrical Contractor:
-
Canopy structure over electric panel at WWTP
-
Confirm 7545 N Broadway house wiring has been changed from 10 gauge to 8 gauge.
-
Items Needed From Contractors:
Carver Construction – General Contractor:
-
As-Builts – Carver to send first sheet to C.T. Male mid next week for approval. Once ok’d, should take @ 1 week.
-
Orenco Training – to be scheduled.
-
Confirm all “Water” caps have been changed to “Sewer” caps.
-
-
Items Needed From C.T. Male:
- None mentioned.
-
Application For Payment Status
o
-
Erosion/Sediment Control
- Restorations in process which will close out any open graded areas.
-
Site Safety
- No issues noted this period.
-
RFIs
- No open RFI’s mentioned.
-
Open Discussion
-
Soap Factory tank needs to be resolved.
-
Firehouse Plaza – Carver to do paving per contract. Manhole cover needs to be lowered.
-
Underground Fuel Tank – stockpiled excavated soils – comments received yesterday by Carver. After reviewing, Carver will update via email. If all okay, soil to be removed.
-
USDA Jessica DiDomineck made a Substantial Completion site visit on Monday, April 10 as scheduled. Mayor Smythe toured her around. She was able to obtain the photos needed from her visit.
-
Fernando asked about the Village’s security alarm system for the generators. He will follow up with Vector Security to schedule a site visit to finalize hook up of new generator alarm system.
-
-
Open/Incomplete Items
-
Final restoration/paving/sidewalk replacement.
-
7545 N Broadway – 10 gauge changed to 8 gauge.
-
Canopy structure on top of main panel board.
-
Soil removal from underground fuel tank work at 17 East Market.
-
Confirm “water” caps are all replaced with “sewer” caps.
-
Schedule Orenco training.
-
Confirm status and resolution for Soap Factory tank.
-