Red Hook WatchIndependent Community Resource

Tradition Amended Site Plan Cottage A Elevation

Meetings/Resolutions/(operational)
One-time (complete)operationalone_timeAccept changes to the front elevation of Cottage A and materials as an amendment to the Tradition Site Plan.
First seen
2023-11-06
Latest event
2023-11-06
adopted
Expires

Resolution text

RESOLVED

  1. the materials and front elevation changes to Cottage A are accepted as an amendment to the Site Plan

Lifecycle (1 event)

2023-11-06adoptedvote: unanimous
Approve a resolution to accept materials as an amendment to the Tradition Site Plan for Cottage A Elevation redesign.
moved by Smythe · seconded by Coleman
Show text snapshot for this event
Resolved
  1. the materials and front elevation changes to Cottage A are accepted as an amendment to the Site Plan
Subject key: tradition_site_plan_cottage_a