RESOLUTION AUTHORIZING THE SOLICITATION OF BIDS FOR ST. MARGARET'S ACCESSIBILITY IMPROVEMENTS

One-time (complete)formal_resolutionone_timeThe Town Board authorizes the solicitation of bids for St. Margaret's Accessibility Improvements, with bids due September 19, 2024, to be funded by a FY 2023 CDBG grant in the amount of $100,000.
First seen
2024-08-28
Latest event
2024-08-28
adopted
Expires

Resolution text

RESOLVED

  1. the Town Board of the Town of Red Hook does hereby authorize and direct the solicitation of bids for the Project, with bids to be received until September 19th, 2024 or such later time and date as determined by the Supervisor, provided that such publication shall appear not less than five days prior to the date set for bid opening
Show preamble — 2 WHEREAS clauses
  • WHEREAS, Town Engineer Tighe & Bond has prepared plans and specification to solicit bids for the "ST. MARGARET's ACCESSIBILITY IMPROVEMENTS" in the Town (the "Project")
  • WHEREAS, a portion of such project is expected to be paid from FY 2023 CDBG grant funds in the amount of $100,000

Lifecycle (1 event)

2024-08-28adoptedvote: unanimous
Authorize the solicitation of bids for St. Margaret's Accessibility Improvements with a bid opening date of September 19, 2024, using FY 2023 CDBG grant funds.
moved by McKeon · seconded by Kane
Show text snapshot for this event
Resolved
  1. the Town Board of the Town of Red Hook does hereby authorize and direct the solicitation of bids for the Project, with bids to be received until September 19th, 2024 or such later time and date as determined by the Supervisor, provided that such publication shall appear not less than five days prior to the date set for bid opening
Whereas
  • WHEREAS, Town Engineer Tighe & Bond has prepared plans and specification to solicit bids for the "ST. MARGARET's ACCESSIBILITY IMPROVEMENTS" in the Town (the "Project")
  • WHEREAS, a portion of such project is expected to be paid from FY 2023 CDBG grant funds in the amount of $100,000
Subject key: st_margarets_accessibility_improvements