RESOLUTION REGARDING SEWER AND WATER SYSTEM PERFORMANCE BOND REDUCTION FOR TRADITION AT RED HOOK SECTION 7
Activeformal_resolutionongoingThe Town Board authorizes reduction of the performance bond for Section 7 sewer and water improvements of the Tradition at Red Hook project from $197,144.00 to $39,428.80 and conversion to a maintenance bond, based on DCWWA and DCDBH certifications that the improvements have been satisfactorily completed.
First seen
2023-07-11
Latest event
2023-07-11
adopted
Expires
—
Resolution text
RESOLVED
- Based on the correspondence from DCWWA and the authorization to Operate from DCDBH for the completed sewer and water improvements for Section 7 of the Project, the required bond amount for Section 7 may be reduced to $39,428.80 and converted to a maintenance bond.
- The Project remains subject to all other applicable requirements of Resolution #39 of 2022 as to Section 7.
- The Supervisor and Town Engineer may take all steps reasonable and necessary in consultation with the Attorney for the Town to implement the intent of this resolution.
Show preamble — 3 WHEREAS clauses
- WHEREAS, as a condition of Resolution #39 of 2022 adopted June 22, 2022, the developer of the Tradition at Red Hook, a 102 lot subdivision project to be developed in sections (formerly known as Hoffman TND project) (the "Project") delivered to the Town Clerk a counterpart of a dual oblige bond in the amount of $197,144.00 for Section 7 water and sewer improvements, of which $6,888.00 is for water and $190.256.00 is for sewer, pursuant to a Memorandum of Understanding ("MOU") with DCWWA (collectively the "DCWWA Performance Bonds")
- WHEREAS, by letter dated June 28, 2023, the DCWWA has determined that the Project has met all conditions of the MOU for the sewer and water systems serving any properties in Section 7 subject to provision of a maintenance bond in the amount of 20% of the construction cost
- WHEREAS, by letter dated June 28, 2023, the Dutchess County Department of Behavioral Health ("DCDBH") has notified the Town Board that the sewer and water improvements contemplated under Section 7 of the Project have been satisfactorily completed and that an Authorization to Operate has been authorized.
Lifecycle (1 event)
2023-07-11adoptedvote: unanimous
Resolution regarding reduction of sewer and water system performance bond for Tradition at Red Hook Section 7 from $197,144.00 to $39,428.80.
moved by McKeon · seconded by Hamel
Show text snapshot for this event
Resolved
- Based on the correspondence from DCWWA and the authorization to Operate from DCDBH for the completed sewer and water improvements for Section 7 of the Project, the required bond amount for Section 7 may be reduced to $39,428.80 and converted to a maintenance bond.
- The Project remains subject to all other applicable requirements of Resolution #39 of 2022 as to Section 7.
- The Supervisor and Town Engineer may take all steps reasonable and necessary in consultation with the Attorney for the Town to implement the intent of this resolution.
Whereas
- WHEREAS, as a condition of Resolution #39 of 2022 adopted June 22, 2022, the developer of the Tradition at Red Hook, a 102 lot subdivision project to be developed in sections (formerly known as Hoffman TND project) (the "Project") delivered to the Town Clerk a counterpart of a dual oblige bond in the amount of $197,144.00 for Section 7 water and sewer improvements, of which $6,888.00 is for water and $190.256.00 is for sewer, pursuant to a Memorandum of Understanding ("MOU") with DCWWA (collectively the "DCWWA Performance Bonds")
- WHEREAS, by letter dated June 28, 2023, the DCWWA has determined that the Project has met all conditions of the MOU for the sewer and water systems serving any properties in Section 7 subject to provision of a maintenance bond in the amount of 20% of the construction cost
- WHEREAS, by letter dated June 28, 2023, the Dutchess County Department of Behavioral Health ("DCDBH") has notified the Town Board that the sewer and water improvements contemplated under Section 7 of the Project have been satisfactorily completed and that an Authorization to Operate has been authorized.
Supersedes
Subject key:
tradition_at_red_hook_performance_bond