Red Hook WatchIndependent Community Resource

RESOLUTION REGARDING SEWER AND WATER SYSTEM PERFORMANCE BOND REDUCTION FOR TRADITION AT RED HOOK SECTIONS 4 AND 5

One-time (complete)formal_resolutionone_timeReduces the required performance bond for water and sewer improvements in Sections 4 and 5 of the Tradition at Red Hook project to $90,175.20, contingent on completion of improvements and subject to all other requirements of Resolution 46 of 2021.
First seen
2022-08-18
Latest event
2022-08-24
adopted
Expires

Resolution text

RESOLVED

  1. Based on the correspondence from DCWWA and the report of the Town Engineer of the completed sewer and water improvements for Sections 4 and 5 of the Project, the required bond amount for Sections 4 and 5 may be reduced to $90,175.20.
  2. The Project remains subject to all other applicable requirements of Resolution #46 of 2021 as to Sections 4 and 5.
  3. The Supervisor and Town Engineer may take all steps reasonable and necessary in consultation with the Attorney for the Town to implement the intent of this resolution.
Show preamble — 3 WHEREAS clauses
  • WHEREAS, as a condition of Resolution #46 of 2021 adopted August 10, 2021, the developer of the Tradition at Red Hook, a 102 lot subdivision project to be developed in sections (formerly known as Hoffman TND project) (the "Project") delivered to the Town Clerk a counterpart of a dual oblige bond in the amount of $450,876.00 for Sections 4 and 5 water and sewer improvements, of which $141,684.00 is for water and $309,192.00 is for sewer, pursuant to a Memorandum of Understanding ("MOU") with DCWWA (collectively the "DCWWA Performance Bonds")
  • WHEREAS, by letter dated August 1, 2022, the DCWWA has determined that the Project has met all conditions of the MOU for the sewer and water systems serving any properties in Sections 4 and 5, subject to provision of a maintenance bond in the amount of 20% of the construction cost
  • WHEREAS, by letter dated August 3, 2022, the Town Engineer has notified the Town Board that the sewer and water improvements contemplated under Sections 4 and 5 of the Project have been satisfactorily completed, and that it is recommended that the bond amounts required for Sections 4 and 5 be reduced accordingly

Lifecycle (2 events)

2022-08-18adoptedvote: 3-0
Reduce the performance bond for Tradition at Red Hook Sections 4 and 5 water and sewer improvements from $450,876.00 to $90,175.20 based on completion of improvements.
moved by McKeon · seconded by Hamel
Show text snapshot for this event
Resolved
  1. Based on the correspondence from DCWWA and the report of the Town Engineer of the completed sewer and water improvements for Sections 4 and 5 of the Project, the required bond amount for Sections 4 and 5 may be reduced to $90,175.20.
  2. The Project remains subject to all other applicable requirements of Resolution #46 of 2021 as to Sections 4 and 5.
  3. The Supervisor and Town Engineer may take all steps reasonable and necessary in consultation with the Attorney for the Town to implement the intent of this resolution.
Whereas
  • WHEREAS, as a condition of Resolution #46 of 2021 adopted August 10, 2021, the developer of the Tradition at Red Hook, a 102 lot subdivision project to be developed in sections (formerly known as Hoffman TND project) (the "Project") delivered to the Town Clerk a counterpart of a dual oblige bond in the amount of $450,876.00 for Sections 4 and 5 water and sewer improvements, of which $141,684.00 is for water and $309,192.00 is for sewer, pursuant to a Memorandum of Understanding ("MOU") with DCWWA (collectively the "DCWWA Performance Bonds")
  • WHEREAS, by letter dated August 1, 2022, the DCWWA has determined that the Project has met all conditions of the MOU for the sewer and water systems serving any properties in Sections 4 and 5, subject to provision of a maintenance bond in the amount of 20% of the construction cost
  • WHEREAS, by letter dated August 3, 2022, the Town Engineer has notified the Town Board that the sewer and water improvements contemplated under Sections 4 and 5 of the Project have been satisfactorily completed, and that it is recommended that the bond amounts required for Sections 4 and 5 be reduced accordingly
2022-08-24adoptedvote: 3-0
Reduce the performance bond for Tradition at Red Hook Sections 4 and 5 from $450,876.00 to $90,175.20 based on completion of sewer and water improvements.
moved by McKeon · seconded by Hamel
Show text snapshot for this event
Resolved
  1. Based on the correspondence from DCWWA and the report of the Town Engineer of the completed sewer and water improvements for Sections 4 and 5 of the Project, the required bond amount for Sections 4 and 5 may be reduced to $90,175.20.
  2. The Project remains subject to all other applicable requirements of Resolution #46 of 2021 as to Sections 4 and 5.
  3. The Supervisor and Town Engineer may take all steps reasonable and necessary in consultation with the Attorney for the Town to implement the intent of this resolution.
Whereas
  • WHEREAS, as a condition of Resolution #46 of 2021 adopted August 10, 2021, the developer of the Tradition at Red Hook, a 102 lot subdivision project to be developed in sections (formerly known as Hoffman TND project) (the "Project") delivered to the Town Clerk a counterpart of a dual oblige bond in the amount of $450,876.00 for Sections 4 and 5 water and sewer improvements, of which $141,684.00 is for water and $309,192.00 is for sewer, pursuant to a Memorandum of Understanding ("MOU") with DCWWA (collectively the "DCWWA Performance Bonds")
  • WHEREAS, by letter dated August 1, 2022, the DCWWA has determined that the Project has met all conditions of the MOU for the sewer and water systems serving any properties in Sections 4 and 5, subject to provision of a maintenance bond in the amount of 20% of the construction cost
  • WHEREAS, by letter dated August 3, 2022, the Town Engineer has notified the Town Board that the sewer and water improvements contemplated under Sections 4 and 5 of the Project have been satisfactorily completed, and that it is recommended that the bond amounts required for Sections 4 and 5 be reduced accordingly

Supersedes

Subject key: tradition_at_red_hook_performance_bond