Phase II Public Intent Statement for Water Project
One-time (complete)operationalone_timeApproves the Public Intent Statement indicating the Village of Red Hook intends to file an application with USDA Rural Development for Phase II water project improvements, estimated cost $3.8 million to be funded by USDA loan at 2.75% interest for 38 years.
First seen
2013-08-05
Latest event
2013-08-05
adopted
Expires
—
Resolution text
RESOLVED
- Approve Phase II Public Intent Statement for USDA Rural Development water project funding application.
Document references
Cited by
- 2013-08-05Phase II Water Upgrades USDA ApplicationTwo distinct board actions on the same project: one authorizes submission of the USDA application, the other approves the public intent statement required as part of that application process.
- 2014-05-12Authorization for Mayor to Execute USDA-RD Phase II Water Project Application DocumentsDocument B (public intent statement approval) and Document A (authorization to execute application documents) are separate board actions in sequence within the same funding process but occupy different slots: B approves the intent statement, A authorizes execution of application paperwork.
Lifecycle (1 event)
2013-08-05adoptedvote: unanimous
Approve Phase II Public Intent Statement for USDA Rural Development water project funding application.
moved by Kovalchik · seconded by Norris
Show text snapshot for this event
Resolved
- Approve Phase II Public Intent Statement for USDA Rural Development water project funding application.
Subject key:
phase_ii_water_upgrades