Red Hook WatchIndependent Community Resource

CHIPS-funded drywell and sidewalk repair contract award

Meetings/Resolutions/(operational)
One-time (complete)operationalone_timeAward drywell and sidewalk repair work to Frank Vosburgh & Sons for $23,150 (excluding item #3 which is not CHIPS-funded), contingent upon verification that all bids include required materials and confirmation of material availability, funded from the 2008-2009 CHIPS allocation of $31,026.88 (line item 5110.3).
First seen
2008-06-19
Latest event
2008-06-19
adopted
Expires

Resolution text

RESOLVED

  1. Award CHIPS-funded drywell, swale, and sidewalk repairs to Frank Vosburgh & Sons at the bid price of $23,150, contingent upon review of bid discrepancies and verification that all bid materials are included and available, using 2008-2009 CHIPS allocation (line 5110.3) of $31,026.88.

Lifecycle (1 event)

2008-06-19adoptedvote: unanimous
Approve award of CHIPS-funded drywell and sidewalk repair work to Frank Vosburgh & Sons, contingent upon review of bid discrepancies.
moved by Cohen · seconded by Blundell
Show text snapshot for this event
Resolved
  1. Award CHIPS-funded drywell, swale, and sidewalk repairs to Frank Vosburgh & Sons at the bid price of $23,150, contingent upon review of bid discrepancies and verification that all bid materials are included and available, using 2008-2009 CHIPS allocation (line 5110.3) of $31,026.88.
Subject key: chips_drywell_sidewalk_repair