Building / Planning & Zoning Department Fees

Approved on June 13, 2022

Application / CertificateFee
Residential Construction$0.35 / sf; $100.00minimum
Commercial Construction$0.50 / sf; $200.00minimum
Decks / Porches Open$0.35 / sf; $100.00minimum
Demolition Permit
(when not associatedwith
construction)Residential - $100.00
Garages/Barns - $150.00
Commercial - $200.00
Barns/Pole
Barn/Shed/Detached
Garage$0.35 / sf; $100.00minimum
Solar Energy Collection
Systems (Photovoltaic
Panels), Roof or Ground
Mounted$0.35 / sf; $100.00minimum
Roof Mounted, building permit only.
Ground Mounted by
Planning BoardApproval
Fence Permits$100.00/ 1st100linearfeet
$0.35 thereafter
AgriculturalStructures
(Proof of Ag
Exemption/Status
Required at time of
Submission.N/A
Building without a
Building Permit
(Post Built Permit)Double the Calculated Fee
Certificate of OccupancyCollect with Building Permit Application
$50.00Residential
$100.00Commercial
Abstract C/O /
Municipal Search$100.00

Village of Red Hook

Building / Planning & Zoning Department Fees

Approved on June 13, 2022

|Driveway Permit

(Village Roads)$100.00
Generator$75.00
Electrical Work / Upgrade$100.00
Solid Fuel Permit:
Wood, Coal, Pellet$100.00
Operating Permits$100.00
Pools: In-ground, Above
GroundIn Ground $200.00
Above Ground $150.00
Spa/Hot Tubs$100.00
Sign Permit$100.00flat
Fire Inspections$100.00 PER UNIT up to 2,500 sf;
2,501—5,000 sf=$150.00
5,001–10,000 sf=$200.00
Roof Repair / Replacement$100.00 for Residential ONLY
SEE NEW SCHEDULE
ATTACHED FOR
COMMERICAL STRUCTURES
Oil Tank Abandonment/
Replacement
(inside or underground)$100.00
Planning Board:
SITE PLAN REVIEW$200.00 w/ SEAF; $300.00 w/ FEAF
Allmailingsto be donebyapplicantReceipts reviewed at
Meetingfor
completeness

Village of Red Hook

Building / Planning & Zoning Department Fees

Approved on June 13, 2022

Planning Board: MINOR SUBDIVISION & $300.00 plus $150.00/lot Planning Board: MAJOR SUBDIVSION Planning Board: LOT LINE $200.00 ADJUSTMENT Receipts reviewed at Zoning Board: $100.00 plus all mailings to be done by meeting for AREA VARIANCE Applicant completeness Receipts reviewed at Zoning Board: $100.00 plus all mailings to be done by meeting for USE VARIANCE Applicant completeness Zoning Board: $50.00 Interpretation SEQRA: SEAF $200.00 SEQRA: FEAF $300.00

ESCROW MAY BE REQUESTED BY PLANNING & ZBA BOARDS PER VILLAGE OF RED HOOK ZONING §200-54

FIRE INSPECTIONS:

In the event the Fire Inspector is required to inspect premises a third time to ensure compliance with the Code an additional fee of $100.00 is to be charged

In the event the Fire Inspector is required to inspect premises a fourth time to ensure compliance with the Code an additional fee of $125.00 is to be charged

In the event of non-compliance with the Fire Inspector's Recommendations after a fourth visit the property owner will be subject to fines and expenses imposed by the Village Justice Court per Village Code Chapter 95.