Red Hook WatchIndependent Community Resource

Thursday, September 15, 2022

Meetings/2022-09-15
Water Board · Workshop meeting

workshopWater Board Work Session Summary

13 agenda items · 0 motions · 0 substantive · 0 formal resolutions
Minutes for this meeting have not yet been posted. Only the agenda is available; check back in 2–6 weeks.

Agenda (13 items)

Order reflects how the Board actually took items up at the meeting (which sometimes differs from the posted agenda — e.g. items brought forward when a guest is present).

#1Well levelsInformational
Report on water well resting levels for Well 1 (50 feet) and Well 2 (35 feet).
Action
Expected: info_only
Report on water well resting levels for Well 1 (50 feet) and Well 2 (35 feet).
#2Pump VolumesInformational
Report on pump volumes for Well 1 (92 GPM) and Well 2 (94 GPM); note that new pump and motor for Well 2 are installed and operating satisfactorily.
Action
Expected: info_only
Report on pump volumes for Well 1 (92 GPM) and Well 2 (94 GPM); note that new pump and motor for Well 2 are installed and operating satisfactorily.
#3Coliform ReportInformational
Report that no coliform bacteria were detected in August 2022 water testing.
Action
Expected: info_only
Report that no coliform bacteria were detected in August 2022 water testing.
#4Turbidity (NTU)Informational
Report turbidity level of 0.05 NTU (Nephelometric Turbidity Units), below the 1.0 required threshold.
Action
Expected: info_only
Report turbidity level of 0.05 NTU (Nephelometric Turbidity Units), below the 1.0 required threshold.
#5Chlorine ResidualInformational
Report chlorine residual level of 0.7 PPM (parts per million), below the 1.0 goal.
Action
Expected: info_only
Report chlorine residual level of 0.7 PPM (parts per million), below the 1.0 goal.
#62022 Water Test RequirementsInformational
Report on status of required annual and periodic water quality testing: PFOS and PFOA completed August 2022; DIOXANE due by December 1, 2022; Asbestos due by December 31, 2030; Lead and Copper due by September 30, 2024; Nitrate, POC, and MTBE due by December 31, 2022; Disinfection by-products (THMS and HAA5) completed August 2022.
Action
Expected: info_only
Report on status of required annual and periodic water quality testing: PFOS and PFOA completed August 2022; DIOXANE due by December 1, 2022; Asbestos due by December 31, 2030; Lead and Copper due by September 30, 2024; Nitrate, POC, and MTBE due by December 31, 2022; Disinfection by-products (THMS and HAA5) completed August 2022.
#7Current InventoryInformational
Report on stock levels and reordering of water treatment supplies: 5-micron filter cartridges (1 in stock, 5 ordered), 1-micron filter cartridges (1 in stock, 5 ordered), top-seals (2 in stock, 5 ordered), and sodium hypochlorite in 5-gallon containers (46 empty, 16 full, ordering).
Action
Expected: info_only
Report on stock levels and reordering of water treatment supplies: 5-micron filter cartridges (1 in stock, 5 ordered), 1-micron filter cartridges (1 in stock, 5 ordered), top-seals (2 in stock, 5 ordered), and sodium hypochlorite in 5-gallon containers (46 empty, 16 full, ordering).
#8Tank InspectionInformational
Report that tank inspection indicates good condition but rehabilitation (painting) or replacement is needed; work with Tighe and Bond to produce RFP for repainting and pursue grant funding for tank replacement.
Action
Expected: discussion
Report that tank inspection indicates good condition but rehabilitation (painting) or replacement is needed; work with Tighe and Bond to produce RFP for repainting and pursue grant funding for tank replacement.
#9Fences: Poison Ivy on fencesInformational
Report that poison ivy removal on fences has been completed; note that treatment will need to be repeated.
Action
Expected: info_only
Report that poison ivy removal on fences has been completed; note that treatment will need to be repeated.
#10Pump and Motor for Well #2Informational
Report that new pump and motor for Well 2 are installed and operating satisfactorily.
Action
Expected: info_only
Report that new pump and motor for Well 2 are installed and operating satisfactorily.
#11Ross Valve: Is due for overhaulInformational
Note that Ross Valve maintenance is due for overhaul.
Action
Expected: discussion
Note that Ross Valve maintenance is due for overhaul.
#12Valve InstallationInformational
Report that Fernando Dongo will investigate installation of a valve in the water main in the Manor/Colonial area.
Action
Expected: discussion
Report that Fernando Dongo will investigate installation of a valve in the water main in the Manor/Colonial area.
#13Lead Service Line InventoryInformational
Report that Fernando Dongo will send information for required online lead service line inventory.
Action
Expected: discussion
Report that Fernando Dongo will send information for required online lead service line inventory.

Documents prepared for this meeting (2)