Generator Preventative Maintenance Contract
The Mayor is authorized to sign the ElectricAce Operations LLC Generator Preventative Maintenance 5-year contract covering all four Village-owned generators.[15]
2025
Wastewater Treatment Plant Security System
The Mayor is authorized to engage with Vector Security for security panel installation and a monthly monitoring service plan at both the old and new Wastewater Treatment Plants.[14]
2024
Vanguard Cleaning Weekly Service Contract
Unifirst Area Rugs and Mats Agreement
The Mayor is authorized to sign a Customer Service Agreement with Unifirst for the provision of high-traffic area rugs and mats.[9]
Septic Tank and Grease Trap Hauling Contract
Superior Sanitation is awarded the 2024–2027 Septic Tank & Grease Trap Pump Out & Hauling contract (RFP #2024-02) at a total cost of $106,131.84. The contract expires December 31, 2027.[10]
2022
Village Office Building Hours
Village of Red Hook Office Building hours are set at 11am–4pm, Monday through Friday.[3]
Otis Elevator Maintenance Contract
The Village has approved the Otis Maintenance plan proposal for a 10-year contract at $3,000 annually for maintenance and service of the Village Hall elevator. The contract runs through December 12, 2032.[4]
History · superseded or expired
2025
Allstate Power Systems Preventative Maintenance Contract (Three Generators, 2025)
The Mayor was authorized to sign a Preventative Maintenance Contract with Allstate Power Systems, LLC covering three of the four Village-owned generators. Superseded by the updated Allstate contract and then by the ElectricAce 5-year contract.[12]
Allstate Power Systems Updated Generator Maintenance Contract (April 2025)
The Mayor was authorized to sign an updated contract for generator preventative maintenance services with Allstate Power Systems. Superseded by the ElectricAce Operations LLC 5-year contract.[13]
2024
Allstate Power Systems Generator Service Contract (2024)
The Mayor was authorized to sign an annual service contract with Allstate Power Systems for generator service at Village Hall, water plant, and wastewater treatment plant. Superseded by the 2025 Allstate Preventative Maintenance Contract and then by the ElectricAce contract.[8]
2023
AllState Power Systems Contract (Wastewater Generator Coverage)
The Mayor was authorized to sign the AllState Power Systems contract as amended to include coverage for the new generator at the wastewater treatment facility. Superseded by the 2024 and 2025 Allstate contracts and ultimately by the ElectricAce contract.[5]
2023–2024 Septic Tank and Grease Trap Hauling Contract
The Mayor was authorized to execute the 2023–2024 Septic Tank & Grease Trap Pump Out & Hauling Contract with Superior Sanitation. Expired December 31, 2024; superseded by the 2024–2027 contract.[6]
2022
Wastewater Treatment Plant Generator Added to Preventative Maintenance Contract
The wastewater treatment plant generator near Red Hook Commons was added to the Village's Preventative Maintenance Contract for an additional $910. Superseded by subsequent Allstate Power Systems contracts.[2]
2009
Emergency Generator Annual Inspection Contract (Water Facility)
Approved an annual service contract to inspect and maintain the emergency generator at the water facility. Superseded by subsequent Allstate Power Systems contracts and ultimately by the ElectricAce 5-year contract.[1]
Source resolutions
- [1]2009-11-19Emergency generator annual inspection contract
- [2]2022-05-09Generator Added to Preventative Maintenance Contract
- [3]2022-05-25Office Building Hours Change to 11am-4pm
- [4]2022-12-12Otis Elevator Maintenance Contract Approval
- [5]2023-03-13Authorize Mayor to sign AllState Power Systems contract
- [6]2023-04-102023-2024 Septic Tank & Grease Trap Pump Out & Hauling Contract with Superior Sanitation
- [7]2024-03-11Vanguard Cleaning Weekly Service Contract
- [8]2024-03-11Allstate Power Systems Generator Service Contract Authorization
- [9]2024-04-25Customer Service Agreement with Unifirst
- [10]2024-04-25Septic Tank & Grease Trap Hauling Contract Award
- [11]2024-06-20Vanguard Cleaning Contract Price Increase
- [12]2025-02-10Preventative Maintenance Contract with Allstate Power Systems, LLC
- [13]2025-04-14Authorize Mayor to sign Allstate Power Systems generator maintenance contract
- [14]2025-07-28Security system installation authorization
- [15]2026-02-09ElectricAce Generator Preventative Maintenance Contract
Synthesized from the chronological history of these resolutions. Each clause shows the year it was last established or amended. The text is a reading aid — for legal force, consult the source resolutions and the Village Code.