Well restoration and electrical hookup approval
ActiveoperationalongoingApprove reasonable costs for restorations and electrical hookup service to the well, with an RFP to three vendors and annual service contract for generator.
First seen
2009-08-20
Latest event
2009-08-20
adopted
Expires
—
Resolution text
RESOLVED
- Approve reasonable restorations and cost of electrical hookup service to the well
- Issue RFP to three places and establish annual service contract on generator
Lifecycle (1 event)
2009-08-20adoptedvote: unanimous
Approve reasonable restorations and electrical hookup service costs for the well.
moved by Seymour · seconded by Kovalchik
Show text snapshot for this event
Resolved
- Approve reasonable restorations and cost of electrical hookup service to the well
- Issue RFP to three places and establish annual service contract on generator