Red Hook WatchIndependent Community Resource

Water Main Locate Project – Northeast Quadrant

Meetings/Resolutions/(operational)
One-time (complete)operationalone_timeApproves the lowest bidder proposal from New England Subservice for $4,500 to locate water mains in the NE quadrant of the Village.
First seen
2022-07-11
Latest event
2022-07-11
adopted
Expires

Resolution text

RESOLVED

  1. Accept the proposal from New England Subservice for underground locates of water mains in the NE quadrant of the Village at a cost of $4,500.00

Lifecycle (1 event)

2022-07-11adopted
Authorize acceptance of the proposal from New England Subservice for underground water main locates in the NE quadrant of the Village at the low bid amount of $4,500.00.
moved by Smythe
Show text snapshot for this event
Resolved
  1. Accept the proposal from New England Subservice for underground locates of water mains in the NE quadrant of the Village at a cost of $4,500.00
Subject key: water_main_locates_northeast