Selection of Engineer for Block Grant Sidewalk Project

Meetings/Resolutions/(operational)
One-time (complete)operationalone_timeThe Village Board selects CT Male and Associates as the engineer for the 2015 Block Grant sidewalk project following a competitive bidding process.
First seen
2015-05-28
Latest event
2015-05-28
adopted
Expires

Resolution text

RESOLVED

  1. CT Male and Associates is selected as the winning bidder for the engineering services
  2. the printed documents are to be filed in the Clerk's office
Show preamble — 3 WHEREAS clauses
  • WHEREAS, the Village advertised for RFP's for the Block Grant sidewalk project 2015
  • WHEREAS, 3 bids were opened at the Workshop meeting May 21, with bidders Fusco Engineering ($7,000), Morris and Associates ($6,150), and CT Male and Associates ($4,500)
  • WHEREAS, the Village Board has reviewed the submissions

Lifecycle (1 event)

2015-05-28adoptedvote: unanimous
Select CT Male and Associates as the engineer for the Block Grant sidewalk project 2015 at a bid of $4,500.
moved by Blundell · seconded by Zacharzuk
Show text snapshot for this event
Resolved
  1. CT Male and Associates is selected as the winning bidder for the engineering services
  2. the printed documents are to be filed in the Clerk's office
Whereas
  • WHEREAS, the Village advertised for RFP's for the Block Grant sidewalk project 2015
  • WHEREAS, 3 bids were opened at the Workshop meeting May 21, with bidders Fusco Engineering ($7,000), Morris and Associates ($6,150), and CT Male and Associates ($4,500)
  • WHEREAS, the Village Board has reviewed the submissions
Subject key: sidewalk_project_engineer_2015