One-time (complete)operationalone_timeTransfers $2,500.00 from contingency funds to cover Phase I Water Form A-133 Audit costs up to $12,500.00.
First seen
2014-04-14
Latest event
2014-04-14
adopted
Expires

Resolution text

RESOLVED

  1. $2,500.00 is moved from contingency funds to cover the Phase I Water Form A-133 Audit cost up to $12,500.00

Lifecycle (1 event)

2014-04-14adoptedvote: unanimous
Move $2,500.00 from contingency for Phase I Water Form A-133 Audit to cover cost up to $12,500.00.
moved by Kovalchik · seconded by Norris
Show text snapshot for this event
Resolved
  1. $2,500.00 is moved from contingency funds to cover the Phase I Water Form A-133 Audit cost up to $12,500.00