RESOLUTION TO APPROVE WWTP CAPACITY STUDY BY DELAWARE ENGINEERING USING ARPA FUNDS
One-time (complete)formal_resolutionone_timeThe Board approves a $15,000 feasibility study by Delaware Engineering to assess options for expanding wastewater treatment plant capacity, to be funded from available ARPA funds.
First seen
2023-11-13
Latest event
2023-11-13
adopted
Expires
—
Resolution text
RESOLVED
- The proposal for a feasibility study to increase the WWTP capacity is approved to proceed for a cost of $15,000
- The cost will be covered using ARPA funds
Show preamble — 5 WHEREAS clauses
- WHEREAS, the new WWTP, Plant "A" (or BK for Brent Kovalchik), has a total capacity of 50,000 gallons per day
- WHEREAS, Plant BK is running at about 40,000 gallons per day usage now
- WHEREAS, there are several requests and expressions of interest in being added to the Sewer Use Area including two significant development projects in the planning stages that will require additional WWTP capacity
- WHEREAS, the Village engineers, Delaware Engineering has proposed a feasibility study to increase the WWTP capacity, looking at the full potential need and capacity to create a long term plan for expansion
- WHEREAS, the Village has unused ARPA funds that can cover these one-time costs
Document references
Cites or incorporates
- 2024-06-10Resolution to Authorize Submittal of Sewer Phase Ii Project for Listing on the Clean Water State Revolving Fund Intended Use Plan (Iup)
- 2024-06-10Resolution to Authorize Submittal of Sewer Phase II Project for Listing on the Clean Water State Revolving Fund Intended Use Plan (IUP)
- 2024-07-15Resolution to Authorize Submission of Consolidated Funding Application (CFA) Grant Application for Sewer Phase Ii Project
- 2024-07-11Resolution to Authorize Submission of Consolidated Funding Application (CFA) Grant Application for Sewer Phase II Project
- 2024-10-07Village of Red Hook Monthly Reports — September 2024
- 2025-04-10Village of Red Hook Monthly Reports — March 2025
- 2025-05-08Sewer Department Monthly Report — April 2025
- 2025-07-28Resolution to Authorize Submission of Consolidated Funding Application (CFA) Grant for Sewer Phase Ii Project
- 2025-07-28Resolution to Authorize Submission of Consolidated Funding Application (CFA) Grant for Sewer Phase II Project
Lifecycle (1 event)
2023-11-13adoptedvote: 4-0
Approve a $15,000 feasibility study by Delaware Engineering to evaluate wastewater treatment plant capacity expansion, funded by ARPA funds.
moved by Bradley-Rickard · seconded by Appenzeller
Show text snapshot for this event
Resolved
- The proposal for a feasibility study to increase the WWTP capacity is approved to proceed for a cost of $15,000
- The cost will be covered using ARPA funds
Whereas
- WHEREAS, the new WWTP, Plant "A" (or BK for Brent Kovalchik), has a total capacity of 50,000 gallons per day
- WHEREAS, Plant BK is running at about 40,000 gallons per day usage now
- WHEREAS, there are several requests and expressions of interest in being added to the Sewer Use Area including two significant development projects in the planning stages that will require additional WWTP capacity
- WHEREAS, the Village engineers, Delaware Engineering has proposed a feasibility study to increase the WWTP capacity, looking at the full potential need and capacity to create a long term plan for expansion
- WHEREAS, the Village has unused ARPA funds that can cover these one-time costs
Subject key:
wwtp_capacity_expansion_study