COMMUNIPARK – FUNDING STATEMENT WITH RESOLUTION – Line of Credit and Grant
One-time (complete)formal_resolutionone_timeAuthorizes the Village Treasurer to utilize a line of credit from Salisbury Bank at 3% interest up to $45,000 to pay for municipal parking lot improvements, with repayment from DASNY grant reimbursement.
First seen
2019-06-20
Latest event
2019-06-20
adopted
Expires
—
Resolution text
RESOLVED
- the village Treasurer is authorized to utilize the line of credit from Salisbury Bank to pay the direct costs. The Mayor and/or Treasurer are authorized to exercise the line of credit up to the amount of the installation and materials costs, up to $45,000. With line of credit option utilized, the Village will use grant receipt amounts to pay down the line of credit accordingly and reduce the amount borrowed from Salisbury Bank to a $0 balance for this activity.
Show preamble — 5 WHEREAS clauses
- WHEREAS, the Village of Red Hook Board has received the $125,000 NYS DASNY grant to purchase and improve the municipal lot and complied with purchasing standards.
- WHEREAS, the village selected Stat Construction; Hitchcock and Company Electric; F.Vosburg & Son and Keeler Vault to supply and install improvements to the lot for parking and community events with projected costs of approximately $41,000
- WHEREAS, the Village will utilize its Highway Department staff for excavation and trenching, including purchase certain components and at its cost, for the grant reimbursement and/or "in-kind" matching requirements;
- WHEREAS, the DASNY grant is a reimbursement style grant and the Village will incur the costs and then submit for payment to DASNY;
- WHEREAS, the Village also has a line of credit with Salisbury Bank at 3% interest;
Lifecycle (1 event)
2019-06-20adoptedvote: 4-0
Authorize use of line of credit from Salisbury Bank to fund CommuniPark municipal parking lot improvements with DASNY grant reimbursement.
moved by Blundell · seconded by Trapp
Show text snapshot for this event
Resolved
- the village Treasurer is authorized to utilize the line of credit from Salisbury Bank to pay the direct costs. The Mayor and/or Treasurer are authorized to exercise the line of credit up to the amount of the installation and materials costs, up to $45,000. With line of credit option utilized, the Village will use grant receipt amounts to pay down the line of credit accordingly and reduce the amount borrowed from Salisbury Bank to a $0 balance for this activity.
Whereas
- WHEREAS, the Village of Red Hook Board has received the $125,000 NYS DASNY grant to purchase and improve the municipal lot and complied with purchasing standards.
- WHEREAS, the village selected Stat Construction; Hitchcock and Company Electric; F.Vosburg & Son and Keeler Vault to supply and install improvements to the lot for parking and community events with projected costs of approximately $41,000
- WHEREAS, the Village will utilize its Highway Department staff for excavation and trenching, including purchase certain components and at its cost, for the grant reimbursement and/or "in-kind" matching requirements;
- WHEREAS, the DASNY grant is a reimbursement style grant and the Village will incur the costs and then submit for payment to DASNY;
- WHEREAS, the Village also has a line of credit with Salisbury Bank at 3% interest;
Subject key:
communipark_parking_lot_improvement