Close out of Phase II

One-time (complete)formal_resolutionone_timeAccepts completion of USDA-RD Water Improvement Phase 2 construction and authorizes the Mayor, engineers and financial staff to complete closing procedures with USDA-RD and EFC.
First seen
2017-07-10
Latest event
2017-07-10
adopted
Expires

Resolution text

RESOLVED

  1. that the Village Board of the Village of Red Hook hereby accepts the work of Phase 2 Water Improvement as complete and therefore authorizes its Mayor, engineers and financial staff to complete the appropriate forms and paperwork to move toward a closing with the USDA-RD and EFC
Show preamble — 4 WHEREAS clauses
  • WHEREAS, the final construction work of USDA – RD Water Improvement Phase 2 is physically complete
  • WHEREAS, the two contractors operated under separate contracts – Contract 4G for the General/Prime Contractor (Jersen Construction Inc.); 4E Prime Electrical Contractor (Gross Electric Inc.)
  • WHEREAS, the work has been performed in accord with the contracts and there are no current disputes past or pending
  • WHEREAS, the construction work is completed and is ready for final payment

Lifecycle (1 event)

2017-07-10adoptedvote: unanimous
Accept the completion of Water Improvement Phase 2 construction and authorize the Mayor, engineers, and financial staff to complete closing procedures with USDA-RD and EFC.
moved by Blundell · seconded by Kovalchik
Show text snapshot for this event
Resolved
  1. that the Village Board of the Village of Red Hook hereby accepts the work of Phase 2 Water Improvement as complete and therefore authorizes its Mayor, engineers and financial staff to complete the appropriate forms and paperwork to move toward a closing with the USDA-RD and EFC
Whereas
  • WHEREAS, the final construction work of USDA – RD Water Improvement Phase 2 is physically complete
  • WHEREAS, the two contractors operated under separate contracts – Contract 4G for the General/Prime Contractor (Jersen Construction Inc.); 4E Prime Electrical Contractor (Gross Electric Inc.)
  • WHEREAS, the work has been performed in accord with the contracts and there are no current disputes past or pending
  • WHEREAS, the construction work is completed and is ready for final payment
Subject key: water_phase_2_project