Phase I Water – Resolution of Completion
One-time (complete)formal_resolutionone_timeThe Village Board accepts the completion of Phase I Water Improvement project and authorizes the Mayor, engineers, and financial staff to finalize closing documentation with USDA-RD and EFC.
First seen
2014-07-14
Latest event
2014-07-14
adopted
Expires
—
Resolution text
RESOLVED
- the Village Board of the Village of Red Hook hereby accepts that work of Phase I Water Improvement as complete and therefore authorizes its Mayor, engineers and financial staff to complete the appropriate forms and paperwork to move toward a closing with the USDA-RD and EFC
Show preamble — 4 WHEREAS clauses
- WHEREAS, the final construction work of USDA-RD Water Improvement Phase I is physically complete
- WHEREAS, the three contractors operated under separate contracts - Contract 1 for the General /Prime Contractor (Trinity Construction Inc.); Contract 1E Prime Electrical Contractor (Whalen Electric LLC); Contract 2 was for National Metering Services, Inc.
- WHEREAS, the work has been performed and completed with no disputes in the past or pending
- WHEREAS, the construction work is completed and ready for final payment
Lifecycle (1 event)
2014-07-14adoptedvote: 4-0
Accept the completion of Phase I Water Improvement project and authorize the Mayor, engineers and financial staff to complete forms and paperwork to move toward closing with USDA-RD and EFC.
moved by Blundell · seconded by Kovalchik
Show text snapshot for this event
Resolved
- the Village Board of the Village of Red Hook hereby accepts that work of Phase I Water Improvement as complete and therefore authorizes its Mayor, engineers and financial staff to complete the appropriate forms and paperwork to move toward a closing with the USDA-RD and EFC
Whereas
- WHEREAS, the final construction work of USDA-RD Water Improvement Phase I is physically complete
- WHEREAS, the three contractors operated under separate contracts - Contract 1 for the General /Prime Contractor (Trinity Construction Inc.); Contract 1E Prime Electrical Contractor (Whalen Electric LLC); Contract 2 was for National Metering Services, Inc.
- WHEREAS, the work has been performed and completed with no disputes in the past or pending
- WHEREAS, the construction work is completed and ready for final payment
Subject key:
water_phase_i_completion