Red Hook WatchIndependent Community Resource

Resolution to Adopt Final Revised Apportionment Municipal Sewer System – Phase I

Activeformal_resolutionongoingAdopts the final revised apportionment for the Village of Red Hook Municipal Sewer System Phase I with a gross project cost of $8,500,000.00, establishing the basis for property owner assessments.
First seen
2021-05-17
Latest event
2021-05-17
adopted
Expires

Resolution text

RESOLVED

  1. the Final Revised Apportionment for the Village of Red Hook Municipal Sewer System Phase I is adopted, establishing the basis for assessment calculations among service area properties, with the Village Board retaining authority to reduce assessments if additional funding sources are secured and applied to the project
Show preamble — 2 WHEREAS clauses
  • WHEREAS, the Village of Red Hook Municipal Sewer System Phase I project cost has been revised from the original May 2017 estimate of $4,900,000.00 to $8,500,000.00 due to updated engineering, design, and bidding results
  • WHEREAS, the revised apportionment based on the new project cost must be adopted to establish the Equivalent Dwelling Units (EDUs) and fair apportionment between property owners in the sewer service area

Lifecycle (1 event)

2021-05-17adoptedvote: unanimous
Adopt the Final Revised Apportionment for the Municipal Sewer System Phase I.
moved by Blundell · seconded by Kovalchik
Show text snapshot for this event
Resolved
  1. the Final Revised Apportionment for the Village of Red Hook Municipal Sewer System Phase I is adopted, establishing the basis for assessment calculations among service area properties, with the Village Board retaining authority to reduce assessments if additional funding sources are secured and applied to the project
Whereas
  • WHEREAS, the Village of Red Hook Municipal Sewer System Phase I project cost has been revised from the original May 2017 estimate of $4,900,000.00 to $8,500,000.00 due to updated engineering, design, and bidding results
  • WHEREAS, the revised apportionment based on the new project cost must be adopted to establish the Equivalent Dwelling Units (EDUs) and fair apportionment between property owners in the sewer service area