Authorization for Mayor to Execute USDA-RD Phase II Water Project Application Documents
One-time (complete)formal_resolutionone_timeAuthorizes Mayor Ed Blundell to complete and sign all requisite USDA-RD documents necessary to pursue the Phase II water system improvement project application for preliminary funding determination.
First seen
2014-05-12
Latest event
2014-05-12
adopted
Expires
—
Resolution text
RESOLVED
- Mayor Ed Blundell is fully authorized to complete and sign requisite USDA-RD documents as necessary to complete the Phase II application paperwork
Show preamble — 4 WHEREAS clauses
- WHEREAS, the Village of Red Hook intends to continue its water system upgrades and can apply to USDA-RD for grant/loan money for the Water Improvement Project, Phase II per Preliminary Engineering Report
- WHEREAS, the Village of Red Hook seeks a preliminary funding determination from USDA-RD for Phase II
- WHEREAS, the process involves review and signature of documents to pursue the application for the preliminary funding determination
- WHEREAS, by municipal law the Mayor has executive authority
Document references
Cites or incorporates
- 2013-08-05Phase II Water Upgrades USDA ApplicationDocument B (2013-08-05) is a general authorization to pursue the USDA application; Document A (2014-05-12) is a specific authorization for the Mayor to execute application documents—different slots in the same process (initiate vs. execute), 280 days apart.
- 2013-08-05Phase II Public Intent Statement for Water ProjectDocument B (public intent statement approval) and Document A (authorization to execute application documents) are separate board actions in sequence within the same funding process but occupy different slots: B approves the intent statement, A authorizes execution of application paperwork.
Lifecycle (1 event)
2014-05-12adoptedvote: unanimous
Authorize Mayor to sign USDA-RD documents for Phase II water project application.
moved by Kovalchik · seconded by Norris
Show text snapshot for this event
Resolved
- Mayor Ed Blundell is fully authorized to complete and sign requisite USDA-RD documents as necessary to complete the Phase II application paperwork
Whereas
- WHEREAS, the Village of Red Hook intends to continue its water system upgrades and can apply to USDA-RD for grant/loan money for the Water Improvement Project, Phase II per Preliminary Engineering Report
- WHEREAS, the Village of Red Hook seeks a preliminary funding determination from USDA-RD for Phase II
- WHEREAS, the process involves review and signature of documents to pursue the application for the preliminary funding determination