Red Hook WatchIndependent Community Resource

Resolution to Modify the Usda Form E Budget for the Sewer Project

Meetings/Documents/res::3-2024::2024-01-25::_01252024-430
Inline resolution2024-01-25#3-2024

RESOLUTION TO MODIFY THE USDA FORM E BUDGET FOR THE SEWER PROJECT

Resolution #3-2024 — 2024-01-25

WHEREAS

  • the Sewer Project construction is complete and the contract numbers are being finalized
  • the total Project Cost does not exceed the approved amount however there are adjustments within the line items

RESOLVED

  • the Village Board of Trustees approves the changes to the Project Budget as shown in the line "Modified Budget – Revised" on the attached Form E dated 1/25/24