Red Hook Infrastructure – Sewer Project Monthly Report — January 2024

Meetings/Documents/att::2024-02-12_minutes_432__b03
Attached document2024-02-12

Village of Red Hook Red Hook Infrastructure – Sewer Project Monthly Report January 2024

Red Hook Sewer Project

Substantial Completion was achieved on March 30, 2023. Restoration & Punch List are in the final stages.

General Contract:

  1. Provide record drawing per specification Section 017700.1.5.F. Final edits have been received.

  2. Provide photographic documentation (pre and post work) per Section 013223. Pre photos have been received. A deduction in the contract for the Post photos is included in the Final Change Order (CO#5).

  3. There are a few properties where the grass has not been restored to an acceptable level. Reseeding will take place in Spring 2024. We will withhold an appropriate amount of retainage until complete.

FINANCING

We are working with USDA-RD & EFC on final completion of all paperwork.