Village of Red Hook Water Treatment Facilities Monthly Report
December 1, 2023
System Flow
During the month of November, the water treatment facility treated 6,537,900 total gallons, which is an average of 217,900 gallons per day. See below for the Annual Daily Average Flow Chart:
==> picture [433 x 127] intentionally omitted <==
All bacteriological samples for the month were collected and transported to Pace Analytical Services, Newburgh, New York. Please see below for sample locations and results:
| Location | Total Coliform | E. Coli | ||||
|---|---|---|---|---|---|---|
| 9 Bird | Absent | Absent | ||||
| 2 W. Market | Absent | Absent | ||||
| 55 | Old Farm (Traditions) | Absent | Absent |
Chemical Usage
During the month of November, the water treatment plant used 75 gallons of sodium hypochlorite. The average daily use was 2.4 gallons per day.
If you should have any questions in regards to this report, please feel free to reach out to me at our main office at (845) 244-0129 or by email at Fernando@C3NDEnviro.com
Sincerely, Fernando Dongo Principal Consultant C3ND Environmental Consulting