Village of Red Hook Red Hook Infrastructure – Sewer Project Monthly Report September 2023
Red Hook Sewer Project
Substantial Completion was achieved on March 30, 2023. Restoration & Punch List remain to be completed prior to Final Completion being achieved.
Electrical Contract:
-
Propane tank at WWTP site- schedule start-up training session – scheduled for the week of 9/11/23. Completed
-
Install roof on control panel structure. Work started 10/3 – should be finished by 10/6.
General Contract:
Final property restoration punch list being worked on the week of 10/9.
1.Perform final inspection of each STEP control panel, fix any issues with electrical seals, etc. Carver shall provide a letter stating that they have performed the required final inspection of each control panel.
-
Provide final spare STEP pump as part of spare parts list. All other spare parts have been delivered.
-
Provide required O&M Manuals. Due to be delivered by end of October
-
Provide record drawing per specification Section 017700.1.5.F. Due to be delivered by end of October
-
Provide photographic documentation (pre and post work) per Section 013223. Due to be delivered by end of October
FINANCING
With Form E #11, we have expended $7,819,980.90. That leaves $627,137.10 the majority of which is retainage. Nothing further expended to date.