Water Treatment Facilities Monthly Report — March 6, 2023

Meetings/Documents/att::2023-03-13_minutes_378__b08
Attached document2023-03-13

Village of Red Hook Water Treatment Facilities Monthly Report

March 6, 2023

System Flow

During the month of February, the water treatment facility treated 5,921,500 total gallons, which is an average of 211,500 gallons per day. See below for the Annual Daily Average Flow Chart:

All bacteriological samples for the month were collected and transported to Pace Analytical Services, Newburgh, New York. Please see below for sample locations and results:

LocationTotal ColiformE. Coli
41 CambridgeAbsentAbsent
Traditions MailroomAbsentAbsent
2 West Market2 West MarketAbsentAbsent

Chemical Usage

During the month of February, the water treatment plant used 75 gallons of sodium hypochlorite. The average daily use was 2.4 gallons per day.

If you should have any questions in regards to this report, please feel free to reach out to me at our main office at (845) 244-0129 or by email at Fernando@C3NDEnviro.com

Sincerely,

Fernando Dongo Principal Consultant C3ND Environmental Consulting